Timeline
Judge Doyle Garage Project Information
The following timeline lists the actions/activities to implement the Judge Doyle Square development plan:
City Financial Participation, Land Use Approvals
- Development Agreement to Common Council - July 5, 2016
- Sign Development Agreement - July 15, 2016
- 2017 Executive Capital Budget to Council - Sept 6, 2016
- Board of Estimates Action on Capital Budget - Sept 26, 2016
- Final 2017 Capital Budget Adopted by Council - Nov 14-15, 2016
- Land Use and CSM Approvals/Recordings/Permits - By May 1, 2017
- Public Development Commencement Closing - May, 2017
TID #25 Project Plan Amendment
- Letter to Overlying Taxing JurisdictioN - July 25, 2016
- Introduce Resolution to Common Council - August 2. 2016
- Organizational Joint Review Board Meeting - August, 2016
- Plan Commission Public Hearing and Action - August 29, 2016
- Board of Estimates Action - September 12, 2016
- Common Council Action - September 20, 2016
- Joint Review Board Action - Early Oct, 2016
- Documentation to DOR (deadline) - October 31, 2016
- DOR approval of Project Plan Amendment - First Quarter 2017
Public Ramp Construction
- Design, Bid and Award Public Ramp Construction - July 2016 - September 17
- Demolition of MMB Annex - By May 1, 2017
- Complete Construction of Block 88 Public Ramp - June 2020
- Complete Demolition of Government East Garage on Block 105 - February 2021
Private Development
- By Contract, Commence Block 88 Apartment Element - July 2020
- By Contract, Commence Block 105 Hotel Element - December 2021
- By Contract, Commence 2nd Block 105 Private Development Elements - December 2022