Solar PV - Metro Phase 3

Project Details

  • Location

    • 1101 E. Washington Ave
      Madison, WI 53703
  • Project Type

  • Status

    Completed
  • Estimated Schedule

  • Alder District

    District 6

Project Information

Project Overview

Installation of a roughly 120 kW solar photovoltaic system at the Metro Transit Facility. The system will be roof mounted modules and will produce an estimated 138,000 kWh per year. When combined with the building’s existing roof mounted system, 35% of the building’s electricity usage will be generated by the solar arrays. The array will be installed by the Engineering Division’s GreenPower program where trainees with little to no electrical skills are provide on-the-job training through solar installations on City buildings.

Project Schedule

City User Agencies: Metro Transit

Planning and Design : March – July 2021

1st Advertisement of Bid: N/A

Bid Due Date: N/A

Construction Start Date: August 2021

Expected Completion Date: April 2022

Aerial view of solar photovoltaic system on Metro:

Aerial View Metro Solar

Rooftop view of solar photovoltaic system:

Metro Solar 1