Public Meeting Tuesday March 4 @ 6:30p Re E Main St and S Hancock Street Resurfacing
postedE Main Street and S Hancock Street Resurfacing, Tuesday, March 4:
Please join me for a virtual public information meeting with City Engineering. This meeting will discuss the planned construction of E Main St from S Webster St to S Blair St and S Hancock St from East Washington Ave to south of E Wilson St in 2025. The meeting is scheduled for 6:30 p.m., March 4, 2025, via Zoom. Registration prior is required. March 4, 2025, Public Information Meeting Registration.
A project questionnaire is now available. Please complete by 5 p.m., March 11, 2025.
East Main Street and S Hancock Street Resurfacing Questionnaire
Project Overview
The City is planning construction of E Main St from S Webster St to S Blair St and S Hancock St from East Washington Ave to south of E Wilson St in 2025. The project improvements include replacement of existing pavement and pavement base, sections of curb and gutter, sections of sanitary sewer main and laterals, storm sewer, and water main. Damaged sections of sidewalk will also be replaced or as needed to install sewer service laterals. Additionally, Madison Gas & Electric (MGE) will be replacing the electric duct bank on E Main St. This work will begin under a permit in Spring 2025.
City Process, Meetings
Board of Public Works(link is external) – 4/2/2025 (tentative)
Common Council(link is external) - 4/15/2025 (tentative)
Project Schedule
Start of MGE Construction – May, 2025 (tentative)
Start of City Construction – August, 2025 (tentative)
End of City Construction – June, 2026 (tentative)