Additions

Before starting construction on an addition to your building, there are several steps you will need to take to ensure your addition will be in compliance with zoning and building regulations. Your proposed addition must meet setback requirements and Zoning regulations. If your building is a landmark, in a special district, or has specialized zoning, additional approvals will be required.

Process Overview

  1. Determine Zoning

    The first step of adding onto a non-residential building is to determine if the parcel is zoned for your desired use or if there are any special development considerations for your project.

  2. Submit Plans to Building Inspection

    Where to Go

    Building Inspection Permit Counter by appointment only
    Madison Municipal Building
    215 Martin Luther King Jr. Blvd Suite 017
    Madison, WI 53703

    What to Include

    • Building Plan Approval Application signed by a registered Architect or Engineer
    • Minimum of two sets of scale drawing that are signed and sealed by a registered Architect or Engineer
    • Heat loss calculations
    • Structural calculations
    • Plan review fees need to be paid when the plans are submitted

    Note: If your project cannot conform to building code, follow the variance procedure. See the Petition for Variance Application for more information. Please contact Building Inspection at (608) 266-4551 with any questions.Once the plans have been reviewed and approved, the permit can be issued. If the plans have not been approved, revised plans need to be submitted correcting the items listed in the withhold letter. For more complex projects, the initial plan review will take 10 – 15 business days.

  3. Submit Plumbing Plans

    Plumbing plans are required to be submitted for more than 16 fixtures and must be approved prior to a permit being issued. Plumbing plans are a separate submittal to the Plumbing section. Contact Sean Sutter at (608) 266-4551 with questions.

    Where to Go

    Building Inspection Permit Counter by appointment only
    Madison Municipal Building
    215 Martin Luther King Jr. Blvd Suite 017
    Madison, WI 53703

    What to Include

  4. Submit Plans to Fire Prevention

    The Fire Prevention Division reviews the following:

    • Fire Sprinklers
    • Fire Alarms
    • Kitchen Hood Suppression Systems
    • Standpipe Systems
    • Alternate Fire Extinguishing Systems
    • Access Controlled/Delayed Egress Devices
    • Fire Command Centers
    • High-piled Storage

    There are specific submittal requirements for each type of fire protection system. The requirements vary depending on the type of fire protection system proposed for installation. The Plan Submittal Checklist for Fire Protection System Plans has been provided to assist you in preparing your complete fire protection system plan submittal.

    Where to Go

    City of Madison Fire Department
    314 W. Dayton St.
    Madison, WI 53703

    Hours: Monday – Friday, 8:00 am – 4:30 pm

    Phone: (608) 266-4420

    What to Include

    Flammable/Combustible Liquid Storage Tanks (Under & Above Ground)

    (See Flammable and Combustible Liquids )

    • Installation: Prior to the installation of an underground storage tank or above ground storage tank containing flammable or combustible liquids a Flammable Liquid Tanks Installation Application (SBD-9) must be completed, and along with four sets of drawings and required fees for plan review be forwarded to the State of Wisconsin for tanks 5000 gallons or larger. Tanks smaller than 5000 gallons are reviewed by the Madison Fire Department.
    • Removal/Closure: Prior to the removal or closure of an underground tank or above ground storage tank containing flammable or combustible liquids a City of Madison Tank Closure Application must be completed and forwarded to the Madison Fire Department along with the required drawings and fees at least 15 days prior to any work being performed.

    For further information on tanks contact Cheryl Peterson, Fire Prevention Officer IV at (608) 261-9657.

  5. Get the Permits and Pay the Fees

    After obtaining Zoning and Building approvals a permit can be issued. The permit fee will need to be paid at this time.

    Where to Go

    Building Inspection Permit Counter by appointment only
    Madison Municipal Building
    215 Martin Luther King Jr. Blvd Suite 017
    Madison, WI 53703

    Hours: Monday – Friday, 7:30 am – 4:30 pm

  6. Schedule Inspections

    Once the permits are issued and construction has begun contractors must schedule inspections.

    Building 

    • Footing (before the concrete is poured)
    • Foundation (when forms are removed)
    • Rough framing (before framing is covered)
    • Insulation (before drywall is installed)
    • Final

    Schedule an Inspection

    Call for inspection request: (608) 266-4551.

    Plumbing, HVAC, & Electrical

    • Underground work (before it is covered)
    • Rough (all work in concealed spaces must be visible)
    • Final

    Schedule an Inspection

    To schedule an inspection, call (608) 266-4551, ext. 1. Note: We cannot schedule same-day inspections after 8:30 am.

    Fire Code Requirements

    • Rough (all work in concealed spaces must be visible)
    • Hydrostatic tests
    • Flow tests
    • Final tests

    Schedule a fire Inspection

    To schedule an inspection with Fire, call (608) 266-4420.

  7. Completion

    After final inspections and a completion statement (if required), we will close your permit.