-
Resources for the Madison Community
Madison stands with the families of Abundant Life community. This page is dedicated to connecting victims and the broader community to resources and accurate information about the tragic events that happened on December 16.
Anderson Street
Project Details
Project Information
Latest Update
9/30/2021 Update:
Construction on this project is now complete.
Project Overview
The proposed project is a street resurfacing that will include replacement of existing pavement and storm sewer. In addition, the proposed project will include the installation of new sidewalk and bicycle facilities on the south side of Anderson Street from Wright Street to North Stoughton Road.
The City received bids on April 30, 2020. Speedway Sand and Gravel, Inc. was awarded the bid.
Project Limits
Anderson Street from Wright Street to North Stoughton Road
Project Schedule
Design: Jan. 1, 2020 - June 1, 2020
Construction: June 15, 2020 - Sept. 4, 2020
Public Involvement
There are a number of opportunities during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
Feb. 11, 2020 Public Information Meeting PowerPoint Presentation
Design Option 1
Design Option 2
City Meetings, Process
Board of Public Works: March 4, 2020
Common Council: March 17, 2020