Anderson Street

Last Updated: 06/09/2020

Project Update

6/9/2020: 

Start work notice was sent to properties within the project limits June 2, 2020. Construction is scheduled to start June 15, 2020.

Project Overview

The proposed project is a street resurfacing that will include replacement of existing pavement and storm sewer. In addition, the proposed project will include the installation of new sidewalk and bicycle facilities on the south side of Anderson Street from Wright Street to North Stoughton Road.
The City received bids on April 30, 2020. Speedway Sand and Gravel, Inc. was awarded the bid. 

Project Limits

Anderson Street from Wright Street to North Stoughton Road

Project Schedule

Design:  Jan. 1, 2020-June 1, 2020
Construction:  June 15, 2020- Sept. 4, 2020

Public Involvement

There are a number of opportunities during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Public Information Meetings 

The City held a public information meeting on this project Feb. 11, 2020. 
Feb. 11 Public Information Meeting Presentation
Design Option 1
Design Option 2

City Meetings, Process

Board of Public Works: March 4, 2020
Common Council:  March 17, 2020