Bassett St, N. - 2019

Project Details

  • Location

    • 21 North Bassett Street
      Madison, WI 53703
  • Project Type

  • Status

    Completed
  • Estimated Schedule

  • Impact

    Major
  • Alder District

    District 4

Project Information

Construction Update

Construction is complete for 2019.

Contractor will install high friction surface in 2020.

Project Description

The reconstruction of N. Bassett St. will include replacement of the water main, sanitary sewer main and laterals, installation of new pedestrian scale lighting, and replacement of the pavement, curb, driveway apron, and sidewalk as necessary. The limits of this project are on N. Bassett St. from W. Dayton St. to W. Washington Ave.

This project also includes a test of proposed modifications to the bike lane and parking lane on this portion of N. Bassett St. These proposed changes include moving the bike lane to be adjacent to the curb, and the parking lane will be relocated to be between the right travel lane and the bike lane, away from the curb. The bike lane and parking lane would then be separated by a 2ft. buffer and plastic delineators. These proposed changes are the result of a corridor study. Learn more about the Bassett St corridor study.

Project Schedule

Construction is anticipated to take place from August 22nd to November 8th. MG&E will be performing work in anticipation of the project the week of May 6th.

Project Limits

North Bassett Street - W. Dayton St. to W. Washington Ave.

Public Meetings

The Transportation Department has held several public meetings as part of the corridor study. The next opportunity for public input will be during the Public Hearing at the Board of Public Works on April 3rd.