Bikeways 2022: Path Resurfacings & Bay Creek Bike Improvements
June 1, 2023 Update
Below is an update for the path resurfacings at various locations, note that the schedule changed from what was initially posted.
- Wingra Creek Path: Sections between Olin Ave and John Nolen Dr Underpass: Complete
- Quann Park Path (along W Olin Ave): From Colby St to John Nolen Dr: Complete
- Warner Park Path (along Sheridan Dr): From Warner Park to Woodward Dr: Complete, except for pavement markings
- Sherry Park Path: Sections off of Leon St (from where the Garver Path project ended): Complete, except for pavement markings
- Struck Canyon Underpass Path: From Seybold Rd to Underpass: Work on-going, will be fully opened by Monday, June 5
- Sycamore Park Path: All Paths within Park, including Connector Paths: Not started, work will occur in mid-June
Project Details
Project Information
Project Overview
This project includes a variety of citywide, bike-related improvements and repairs.
Bay Creek Bikeways Improvements
The City is considering creation of a bike boulevard to connect the South Shore and West Shore Dr Bike Blvd to the John Nolen Drive underpass. The new bike boulevard would connect via Lakeside St, Rowell St and Van Deusen St. The City is also considering improvements to the West Shore and South Shore Bike Boulevard.
West South Shore Improvement Information
Citywide Path Resurfacing Projects (planned at the following locations):
Wingra Creek Path: Sections between Olin Ave and John Nolen Dr Underpass
Quann Park Path (along W Olin Ave): From Colby St to John Nolen Dr
Warner Park Path (along Sheridan Dr): From Warner Park to Woodward Dr
Sherry Park Path: Sections off of Leon St (from where the Garver Path project ended)
Struck Canyon Underpass Path: From Seybold Rd to Underpass
Sycamore Park Path: All Paths within Park, including Connector Paths
Project Limits
Citywide Improvements, see Project Overview section for specifics.
Project Schedule
Citywide Path Resurfacings:
Construction: Summer/Fall 2022
Bay Creek Bikeways Improvements:
Planning/Design: Summer 2022
Construction: TBD
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
June 28, 2022 Public Information Meeting Recording
June 28, 2022 Public Information Meeting PowerPoint Presentation
March 31, 2022 Public Information Meeting Recording
March 31, 2022 Public Information Meeting PowerPoint Presentation
If you need an interpreter, translator, materials in alternate formats or other accommodations to access this service, activity or program, please call Aaron Canton of the Engineering Division at 608-242-4763.
Si necesita un intérprete, un traductor, materiales en formatos alternativos u otros arreglos para acceder a este servicio, actividad o programa, comuníquese inmediatamente al número de teléfono que figura a continuación.
Yog tias koj xav tau ib tug neeg txhais lus, ib tug neeg txhais ntawv, cov ntaub ntawv ua lwm yam los sis lwm cov kev pab kom siv tau qhov kev pab, kev ua num los sis kev pab cuam no, thov hu rau tus xov tooj hauv qab no tam sim no.
City Process, Meetings
Citywide Path Resurfacings:
Transportation Commission: May 11, 2022
Board of Public Works: May 25, 2022
Common Council: June 7, 2022
Bay Creek Bikeways Improvements:
Planning: Summer 2022