Blackhawk Tower Radio Equipment Shelter
Project Details
Project Information
Update: October 12, 2020
Photos added for delivery and setting of the pre-fab building on-site. See action photos below!
New Radio and Equipment Shelter
City User Agency: Traffic Engineering
Project Status: Construction!
Construction Start Date: August 2020
Expected Completion Date: October 2020
Construction Progress
July 08, 2020: Staking the site for construction of the footings and foundation:
![BlackhawkEquipTowerSite](https://www.cityofmadison.com/sites/default/files/styles/non_cropped_lg/public/engineering/images/projects/BlackhawkEquipTowerSite.jpg?itok=zRWg2c0v)
August 09, 2020: Forming for the footings:
![BlackhawkEquipTowerFtgs](https://www.cityofmadison.com/sites/default/files/styles/non_cropped_lg/public/engineering/images/projects/BlackhawkEquipTowerFtgs.jpg?itok=SV-Vrt-v)
August 17, 2020: Foundation and grading completed and waiting for the shelter to be delivered:
![BlackhawkEquipTowerFdn](https://www.cityofmadison.com/sites/default/files/styles/non_cropped_lg/public/engineering/images/projects/BlackhawkEquipTowerFdn.jpg?itok=03sbpBmc)
Sept. 24, 2020: The pre-fab building is complete and ready to ship to the project site:
![Blackhawk Tower PreFab Bldg ready to be shipped](https://www.cityofmadison.com/sites/default/files/styles/non_cropped_lg/public/engineering/images/projects/IMG_20200924_141416167_HDR.jpg?itok=G9MLBL2h)
Oct. 08, 2020: Delivery to the site:
October 9, 2020 Setting the pre-fab building at the site:
Completed!