Calypso Rd and Fremont Ave Resurfacing with Utilities
Project Details
Project Information
Calypso Road and Fremont Avenue Resurfacing with Utilities Assessment District - 2018
Construction Update
Calypso is scheduled for paving the week of November 12 and Fremont is scheduled for paving the week of November 26.
Roads are open to local traffic only.
Description
The project consists of new asphalt pavement, and spot replacement of concrete curb and gutter, drive aprons, and sidewalk. Utility replacement will include water main and services with new storm sewer.
Project Limits
Trailsway to Carioca Lane.