Capitol East District Parking Structure
Project Details
Project Information
Follow the progress on our FLICKR page and on the Sky Cam!
Update: July 2, 2019
Added Time Lapse video to the project's Flickr page. View one year of construction in 48 seconds HERE!
City User Agency: Parking Utilities
1st Advertisement of Bids: June 30, 2017
Bid Due Date: August 11, 2017
Construction Start Date: October 02, 2017
Pre-Bid Contractors Meeting: Wednesday, July 26, 2017 from 8:30 -10:30 AM (Please meet in the City-County Building (CCB) at 210 Martin Luther King Jr. Blvd. Conference room 118).
SBE Pre-Bid Meeting: July 28, 2017 1:00 pm at 1600 Emil St., Madison, WI
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
Final Rendering
Project History:
July 18, 2018 Q2 2018 Project Update
The project has continued with the forming and pouring of the concrete structural decks and is currently working on Level 4 of 5 of the parking ramp. The forming and pouring of the concrete structure for the entry lobbies and the commercial portion of the project along E Main St are progressing and the underground site utilities are currently being installed. The concrete framing is scheduled to complete in August.
April 04, 2018 Q1 2018 Project Update
During the 1st quarter of 2018 the project has continued with the foundation work and the underground rough-ins and the vertical work have started.
During April 2018 the slab on grade and the shoring for the elevated decks will begin.
May 16, 2017 File #46812
Capitol East Parking Garage 2017 Budget Amendment
May 10, 2017 File #46095
Urban Design Commission Initial/Final Approval Application
April 18, 2017 File #46812
Capitol East Parking Garage 2017 Budget Amendment
Jan. 31, 2017 Public Open House
Community Open House focused on the design of the Parking Structure.
January 5, 2017 The Capital Times article
Board of Public Works approves Capitol East Parking Garage
November 1, 2016 File #44762
Resolution for a Development Agreement of the “Spark” project, the “Cosmos” project, and the Capitol East District Parking Structure and a contract with Graef-USA Inc. to complete architecture/engineering for a Capitol East District Parking Structure.
September 6, 2016 File #42270
Resolution for contract with Graef-USA Inc. for architecture/engineering services.
March 21, 2016 File #42203
Update on 800 East Washington south block projects and Capitol East Parking Structure.
February 2, 2016 File #41172
Resolution to issue a Request for Proposals for architectural and engineering services.