1. Engineering Downtown Offices Closed to Public, Dec. 26 & 27, 2024.

    Offices will be closed, however, City of Madison Engineering Division staff will be available by phone: 608-266-4751 and email: engineering@cityofmadison.com.

Capitol East District Parking Structure

Project Details

  • Location

    • 800 E Main St
      Madison, WI 53703
  • Project Type

  • Status

    Completed
  • Alder District

    District 6
  • Contract Number

Project Information

Follow the progress on our FLICKR page and on the Sky Cam!


Update: July 2, 2019

Added Time Lapse video to the project's Flickr page.  View one year of construction in 48 seconds HERE!


City User Agency:  Parking Utilities
1st Advertisement of Bids: June 30, 2017
Bid Due Date:  August 11, 2017
Construction Start Date: October 02, 2017
Pre-Bid Contractors Meeting: Wednesday, July 26, 2017 from 8:30 -10:30 AM (Please meet in the City-County Building (CCB) at 210 Martin Luther King Jr. Blvd. Conference room 118).
SBE Pre-Bid Meeting: July 28, 2017 1:00 pm at 1600 Emil St., Madison, WI
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."


Final Rendering

CapEast Rendering

Project History:

July 18, 2018 Q2 2018 Project Update

The project has continued with the forming and pouring of the concrete structural decks and is currently working on Level 4 of 5 of the parking ramp. The forming and pouring of the concrete structure for the entry lobbies and the commercial portion of the project along E Main St are progressing and the underground site utilities are currently being installed. The concrete framing is scheduled to complete in August.

April 04, 2018  Q1 2018 Project Update
During the 1st quarter of 2018 the project has continued with the foundation work and the underground rough-ins and the vertical work have started.
During April 2018 the slab on grade and the shoring for the elevated decks will begin. 

May 16, 2017  File #46812
Capitol East Parking Garage 2017 Budget Amendment

May 10, 2017  File #46095
Urban Design Commission Initial/Final Approval Application

April 18, 2017 File #46812
Capitol East Parking Garage 2017 Budget Amendment

Jan. 31, 2017   Public Open House
Community Open House focused on the design of the Parking Structure.

January 5, 2017  The Capital Times article
Board of Public Works approves Capitol East Parking Garage

November 1, 2016 File #44762
Resolution for a Development Agreement of the “Spark” project, the “Cosmos” project, and the Capitol East District Parking Structure and a contract with Graef-USA Inc. to complete architecture/engineering for a Capitol East District Parking Structure.

September 6, 2016 File #42270
Resolution for contract with Graef-USA Inc. for architecture/engineering services. 
 
March 21, 2016 File #42203
Update on 800 East Washington south block projects and Capitol East Parking Structure. 

February 2, 2016 File #41172
Resolution to issue a Request for Proposals for architectural and engineering services.
 

Was this page helpful to you?