Door Creek Park Shelter
Last Updated: 01/07/2021
Updated Jan. 07, 2021
Updated the proposed Project Schedule - see below
Added Project History - see below
The City of Madison Engineering issued RFP #8860-0-2019-BP, soliciting proposals from qualified vendors for Architect and Engineering Services for Door Creek Shelter. Please visit State of Wisconsin Vendornet or Demandstar by Onvia to register and download the documents. Notification of bid opportunities and corresponding addenda will only be made to subscribers of either one of these two networks.
Project Overview
The Door Creek Park Shelter, located in Door Creek Park, will provide a quality parks facility experience to the Door Creek neighborhood and Madison community. The shelter's primary function will be as a year round-space for community and private events.
Project Schedule
Design and Planning: April - December 2021
1st Advertisement of Bid: Tentative date, December 2022
Bid Tentative due date: January 2023
Construction tentative start date: April 2023
Tentative completion: October 2023