East Dayton Street Resurfacing
Project Details
Project Information
Project Update
9/30/21 Update:
This project is complete.
Project Overview
This project includes the asphalt pavement resurfacing of E Dayton St between N Blair Str and N Livingston St. Spot repairs of curb and gutter, sidewalk, and driveway aprons will be included with this project, as well as utility replacements of storm sewer, sanitary sewer, and water main facilities.
Project Limits
N Blair Street to N Livingston Street
Project Schedule
Design: May 2020
Construction: August 2020
Scheduled Completion: November 2020
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
Public Information Meeting No. 2 was held virtually June 1, 2020.
June 1, 2020 Public Information Meeting PowerPoint Presentation
Public Information Meeting No. 1 was held virtually May 21, 2020.
May 21, 2020 Public Information Meeting PowerPoint Presentation
City Meetings, Process
Common Council Establish Assessment District: May 5, 2020
Board of Public Works Approve Plans, Specs, Assessments: June 3, 2020