Fire Station 10 Retaining Wall
Project Details
Project Information
Latest Update:
May 10, 2022: Project status: Complete. Progress pictures below!
Project Overview
This project will repair the existing limestone retaining wall, which is 50 years old, and original to the building.
Sustainability Goals:
By repairing, rather than replacing the wall with new material, the embodied energy of the project will be significantly reduced.
Project Schedule
City User Agency: City of Madison Fire
Project Status: Construction
2nd Advertisement of Bid: July 8, 2021 RFB 10042-0-2021-BP available on VendorNet or DemandStar.
Bid Due Date: 07/22/2021 @ 2:00 p.m.
Construction Start Date: April 2022
Expected Completion Date: July 2022
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
City Process Meetings
June 02, 2021 File #65577
Awarding Public Works Contract No. 9004, Fire Station 10 Retaining Wall Reconstruction (Single Bid - Not opened)
April 20, 2021 File #64830
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for project known as Fire Station 10 Retaining Wall Reconstruction