Project Overview
The project consists of the replacement of the sanitary sewer, lateral installation and storm sewer improvements. Haywood Drive was reconstructed with new curb and gutter, driveways and new asphalt pavement. Spot replacement of sidewalk was necessary for installation of sewer laterals. Concrete speed humps were also installed as part of reconstruction.
Project Limits
Haywood Drive - North Wingra Drive to North Park Street
Project Schedule
City Work began in early July 2019 and lasted for 2-3 months.