Pumpkin Hollow Sanitary Sewer Impact Fee District
March 29, 2024 Update
Impact Fee Needs Assessment is in the process of being created.
View past project updates »Project Details
Project Information
Project Overview
Install 24” diameter City Sanitary Sewer Interceptor across Interstate I-90/94/39 and then 2 smaller sewer mains from the Interstate up to Hoepker and Portage Road to provide sanitary sewer service to the Pumpkin Hollow Neighborhood Development Plan where there are multiple pending subdivision plat developments.
Project Limits
Project Start Interstate I-90/94/39 (1300’ south of Hoepker Rd) and then 2 smaller sewer mains from the Interstate up to Hoepker and Portage Road.
Public Involvement
With this project being an impact fee project, there will not be a Public Information Meeting for this project. There will be Public Hearing for approval on 6/26/24.
City Process, Meetings Impact Fee Approval
Common Council 6/18/24
Board of Public Works 6/26/24 Public Hearing.
Finance Committee 7/8/2024
Common Council 7/16.24 Impact Fee Ordinance Approval
City Process, Bidding Schedule
First Ad: 8/15/24
BPW Approve Bid: 9/11/24
CC Approve Bid: 9/24/24
Project Start Date: November 11, 2024 thru April 1, 2025 (contractor choice)