Rethke Avenue
Project Details
Project Information
Project Update
10/23/2020 Update:
Construction on this project is complete.
Project Overview
The proposed project is a street reconstruction. Existing pavement, sanitary sewer main, sanitary sewer laterals, storm sewer main, and storm sewer structures will be removed and replaced. New concrete sidewalk, curb and gutter will be installed on both sides of the street.
Project Limits
Rethke Avenue from East Washington Avenue to Commercial Avenue.
Project Schedule
Design - Winter/Spring 2020
Construction - July-October 2020
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
A public information meeting was held March 5, 2020 at Hawthorne Elementary School in Room 113A (Cafeteria), 3344 Concord Avenue, Madison, WI 53714.
Plans Shared at March 5, 2020 Public Information Meeting
March 5, 2020 Public Information Meeting PowerPoint Presentation
Public Hearings, City Meetings
Board of Public Works: March 25, 2020
Common Council: March 31, 2020