Shepard Ter, Chamberlain Ave, Van Hise Ave and Mason St Resurfacing
Project Details
Project Information
Construction Update
Project complete.
Project Description
The general sequence of street construction will go as follows: tree removals, sanitary sewer, water main, storm sewer, asphalt & concrete removals, new retaining wall, new gravel, new curb & gutter, new driveway aprons, new sidewalk, new asphalt paving. It is anticipated that the construction of the sanitary sewer, water main, storm sewer will take 2-3 months. Grading, concrete and asphalt work will take place in June and July.
The project includes street improvements and public utility replacement including sanitary sewer main and laterals. Existing water main will be replaced around the Shepard Terrace cul-de-sac. The remaining water main will not be replaced. Storm sewer inlets will be added to the intersection of Shepard Terrace and Chamberlain Avenue and along Shepard Terrace near the Hoyt Park staircase. The streets in the neighborhood have partial areas of sidewalk and the project will connect these locations of sidewalk together. The proposed sidewalk connections can be found here: Proposed Sidewalk
Project Limits
Shepard Terrace (125’ South of Mason Street to 125’ North of Chamberlain Avenue)
Chamberlain Avenue (Shepard Terrace to N Franklin Avenue)
Van Hise Avenue (Shepard Terrace to N Franklin Avenue)
Mason Street (Shepard Terrace to N Franklin Avenue)
Project Schedule
Construction Spring/Summer: 2019
Public Information Meeting
The City held a public information meeting on Monday, August 13, 2018 at the First Baptist Church, Fellowship Hall, 518 N. Franklin Ave. from 6:00 to 7:00 pm. The presentation from the meeting can be found here: Presentation