1. Resources for the Madison Community

    Madison stands with the families of Abundant Life community. This page is dedicated to connecting victims and the broader community to resources and accurate information about the tragic events that happened on December 16.

Solar PV - Fire Station 09

Project Details

  • Location

    • 201 N. Midvale Blvd.
      Madison, WI 53703
  • Project Type

  • Status

    In Design
  • Estimated Schedule

  • Alder District

    District 5

Project Information

Latest Update

August 01, 2023
Updated project schedule below.

Project Overview

Installation of a roughly 25 kW solar photovoltaic system at Madison Fire Department Station 09. The system will consist of roof mounted modules and will produce an estimated 30,000 kWh per year. Once complete 68% of the building’s electricity usage will be generated by the solar array.  The array will be installed by the Engineering Division’s GreenPower program where trainees with little to no electrical skills are provide on-the-job training through solar installations on City buildings.

Project Schedule

City User Agency: City of Madison Engineering

Planning and Design: January – September 2023

1st Advertisement of Bid: N/A

Bid Due Date: N/A

Construction Start Date: Quarter 3 2025

Expected Completion Date: Quarter 4 2025

Was this page helpful to you?