Solar PV – Fleet Phase 2

Project Details

  • Location

    • 4151 Nakoosa Trail
      Madison, WI 53714
  • Project Type

  • Status

    Completed
  • Estimated Schedule

  • Alder District

    District 3

Project Information

Latest Update

October 04, 2023
Project status: Completed

Project Overview

Installation of a roughly 200 kW solar photovoltaic system at the Fleet Services Main Facility. The system will consist of roof mounted modules and will produce an estimated 250,000 kWh per year. When combined with the building’s existing array, 55% of the building’s electricity usage will be generated by the solar arrays. The array will be installed by the Engineering Division’s GreenPower program where trainees with little to no electrical skills are provide on-the-job training through solar installations on City buildings.

Project Schedule

City User Agency: City of Madison Fleet Services
Design and Planning: Jan – April 2022
1st Advertisement of Bid: N/A
Bid Due Date: N/A
Construction Start Date: April 2022
Expected Completion Date: August 2023

Project Photos

FleetPhase2PV
Phase 2 PV Array Installation
FleetPhase2PV -1
Phase 2 PV Array Installation
FleetPV
Fleet Services Building Solar PV 