Tenney Park Pavilion Acoustic Plaster Ceiling
Project Details
Project Information
Updated: Jan.07, 2021
Expected Completion Date: April 2, 2021
Acoustic Plaster Ceiling
Building construction to install an acoustical plaster ceiling system at the Tenney Park Pavilion. The area of this project is approximately 1,960 square feet.
City User Agency: Parks
Project Status: Construction!
1st Advertisement of Bid: July 17, 2020
Bid Due Date: August 06, 2020
Construction Start Date: Nov. 05, 2020
Expected Completion Date: April 2, 2021
John Wall Family Pavilion in Tenney Park
Pavilion Interior
Project History
Sept. 1, 2020 File #61791
Awarding Public Works Contract No. 8879, Tenney Park Pavilion Acoustical Plaster Ceiling
July 20, 2020 File #60873
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for Tenney Park Pavilion Acoustical Plaster Ceiling