Segoe Rd and Sheboygan Ave Reconstruction
posted
Reconstruction of Segoe Rd and Sheboygan Ave is scheduled to begin on March 20th, and is expected to last until late-August, 2024.
To minimize impact to the community, reconstruction will occur in phases:
Segoe Rd, from University Ave to Regent St, beginning March 20, 2024.
- During construction, this portion of Segoe Rd will remain closed to thru-traffic, with local access for residents maintained.
Sheboygan Ave, from Eau Claire to Segoe Rd, beginning April 29, 2024.
- During construction, this portion of Sheboygan Ave will remain closed to thru-traffic, with local access for residents maintained.
Sheboygan Ave, from Whitney Way to Eau Claire, beginning May 15, 2024.
- During construction, this portion of Sheboygan Ave will remain closed to thru-traffic, with local access for residents maintained.
During the reconstruction, Metro buses will detour from Sheboygan Ave and Segoe Rd.
Additionally, BRT construction on Segoe Rd will begin the week of March 20, 2024 and continue until the week of April 30, 2024.
Learn more about the Segoe Rd and Sheboygan Ave Reconstruction Project.