Resurfacing – Maple Grove Road, Putnam Road and Stratford Drive

posted 

Starting Tuesday, August 13 Payne and Dolan will be reconstructing the asphalt surface on Maple Grove Road from McKee Road to Putnam Road.  Contractors will be working from Chester Drive to McKee Road during the project and will maintain one lane of travel in each direction.

overview map showing closed streets and detour route for resurfacing project on Maple Grove Rd

Project Timeline:

  • The week of 8/13
    • the contractor will be pre-milling and pulverizing the existing asphalt surface in preparation for rough grading.
  • The week of 8/19
    • the contractor will be replacing any poor road base course material.
  • Starting the week of 8/26
    • the contractor will begin the final grading of the street in preparation for asphalt binder and final pavement
  • The week of 9/2
    • final paving will begin

Additionally, Payne and Dolan will also be grading and resurfacing Stratford Drive and Putnam Drive during this time.

Project information is available on Engineering’s Resurfacing Program Webpage.

Was this page helpful to you?