Metro Bus Garage - Roof Replacement
Project Details
Project Information
UPDATE: April 04, 2018
Project Status: Construction
Roof Replacement
The intent of this project is to replace the existing 35 year old, 165,000 ft² EPDM roofing system with a new one that will increase the overall thermal efficiency and provide a 20 year non-prorated warranty from the roofing manufacturer. The scope of this work will consist of the following:
-
The existing ballasted EPDM membrane roofing system shall be removed in sections that shall minimize rain infiltration exposure to the building.
-
Once the existing roof has been removed, the existing steel deck, insulation and plywood shall be inspected and any deteriorated sections shall be replaced on a unit cost basis.
-
Additional wood blocking shall be installed as shown on the plans and specifications.
-
An additional 3”of Polyisocyanurate board insulation will be added over the existing insulation in order to achieve an overall R-value greater than R-20.
-
The existing scuppers shall be enlarged to a minimum opening height of 4”.
-
The existing drains shall be upgraded with cast iron strainers.
-
Obsolete penetrations and a roof hatch that is no longer used shall be removed and covered.
-
Minor repointing of existing brick masonry walls above flashing shall be performed.
-
Thru wall ductwork for one of the roof top units HV5) shall be reworked in order to provide a warrantable penetration.
-
Exhaust fans with low curbs shall be raised to an elevation that allows for a minimum height of 8” between the top of the curb and the final roof elevation.
-
A new 60 mil ballasted roofing system shall be installed.
City User Agency: Madison Metro1st Advertisement of Bids: November 10, 2017 available on BidExpress
Bid Due Date: December 15, 2017
Pre-Bid Site Walk-though: Nov. 29, 2017 1:00 pm at the project site, Madison Metro Bus Garage, located at 1101 E. Washington Ave
SBE Pre-Bid Meeting: Dec. 08, 2017 1:00 pm at 1600 Emil St., Madison, WI
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."Construction Start Date: Anytime after 4/1/18
Expected Completion: May 2019