Lower Badger Mill Creek Pond
April 21, 2025 Update
Shared-Use path and street construction work has resumed following winter shutdown for Blue Harvest Ln, Feather Edge Dr, and Soaring Sky Rn. Over the next approximately 3-4 weeks the Contractor will be installing concrete curb & gutter and sidewalk, finish grading the street and shared-use path, and installing asphalt pavement. Following paving, the contractor will begin site restoration and placement of pavement markings. Alliant will also finish installing street lighting along Blue Harvest Ln, Feather Edge Dr, and Soaring Sky Rn during this time.
View past project updates »Project Details
Project Information
Project Overview
The Stormwater Utility constructed a series of regional detention basins north of Mid Town Road, and east of Meadow Road. The purpose of the ponds is to contain flood water, reducing downstream flooding and minimizing local flood impacts. As part of this project City Engineering is proposing to extend Feather Edge Road from the existing terminus to Meadow Road. The City Parks Division will also be discussing a future master planning effort for the proposed Hill Creek Park expansion.
Project Schedule
Bid Opening: April 25, 2024
Start Date: July 8, 2024
Estimated Final Completion Date: July 3, 2025
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:
Public Information Meetings
- July 26, 2022 Public Information Meeting Recording
- July 26, 2022 Public Information Meeting PowerPoint Presentation
- July 16, 2020 Public Information Meeting PowerPoint Presentation
- May 23, 2018 Public Information Meeting PowerPoint Presentation
City Meetings, Process
Board of Public Works
Approving Plans and Specifications
Common Council