1. Resources for the Madison Community

    Madison stands with the families of Abundant Life community. This page is dedicated to connecting victims and the broader community to resources and accurate information about the tragic events that happened on December 16.

Rethke Avenue

Project Details

  • Location

    • 711 Rethke Avenue
      Madison, WI 53714
  • Project Type

  • Status

    Completed
  • Estimated Schedule

  • Impact

    Minor
  • Alder District

    District 15
  • Contract Number

Project Information

Project Update

10/23/2020 Update:
Construction on this project is complete.

Project Overview

The proposed project is a street reconstruction. Existing pavement, sanitary sewer main, sanitary sewer laterals, storm sewer main, and storm sewer structures will be removed and replaced. New concrete sidewalk, curb and gutter will be installed on both sides of the street.

Project Limits

Rethke Avenue from East Washington Avenue to Commercial Avenue.

Project Schedule

Design - Winter/Spring 2020
Construction - July-October 2020

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Public Information Meetings

A public information meeting was held March 5, 2020 at Hawthorne Elementary School in Room 113A (Cafeteria), 3344 Concord Avenue, Madison, WI 53714.
Plans Shared at March 5, 2020 Public Information Meeting
March 5, 2020 Public Information Meeting PowerPoint Presentation

Public Hearings, City Meetings

Board of Public Works: March 25, 2020

Common Council: March 31, 2020

Was this page helpful to you?