Glenwood Park Railroad Arch Culvert Repair at Southwest Bike Path

Archived Project

This project is complete. This information is available for reference.

July 1, 2024 Update

Work is complete and the site has been restored with topsoil, seed and erosion control matting.  The silt sock inlet control will remain in place until the grass cover is at 70-80%.

View past project updates »

Project Details

Location

  • Glenwood Park
    600 Glenway St
    Madison, WI 53711

Status

Completed

Estimated Schedule

Impact

Minor

Alder District

  • District 13

Contract Number

Glenwood Park

Project Information

The City of Madison Engineering Division will be leading the project which includes deconstructing and reconstructing in-place the existing wall, matching the existing aesthetic and materials, and reusing existing stone when possible on the 1847 stone retaining wall within the WisDOT-owned Southwest Bike Path property adjacent to Glenwood Children’s Park.

Additional information about this project can be found at the Engineering Division's Projects website, located at the following address: https://www.cityofmadison.com/engineering/projects/railroad-arch-culver…

Project Updates

July 1, 2024 Update

Work is complete and the site has been restored with topsoil, seed and erosion control matting.  The silt sock inlet control will remain in place until the grass cover is at 70-80%.

April 17, 2024 Update

Construction fence has been installed at the project location and work is scheduled to begin the week of April 22nd.