N Franklin Avenue & Lynn Terrace Reconstruction with Utilities Project
posted
N Franklin Avenue and Lynn Terrace will be closed to non-local traffic starting on Monday, April 28th. The project will replace aging and deteriorating utilities for N Franklin Avenue and Lynn Terrace.
Details:
- Both areas will fully replace the gravel base and asphalt with spot replacements of curb and gutter, sidewalk, and driveway aprons.
- N Franklin Avenue will also replace the sanitary sewer, storm sewer, and water main.
- Lynn Terrace will also replace the sanitary main and laterals, and storm sewer inlets.
The project is anticipated to be completed in mid-September.

Learn more details and background about the N Franklin Avenue Project.