1. Resources for the Madison Community

    Madison stands with the families of Abundant Life community. This page is dedicated to connecting victims and the broader community to resources and accurate information about the tragic events that happened on December 16.

Yahara Hills Golf Course Redesign

October 22, 2024 Update

Work began on Hole 10. There will be 3 new tees as part of the new design.  The back 2 tees were moved 50 yards to the east to create a dogleg for the hole and bring the water more into play.  A new forward tee was built approximately 240 yards from the green.

New tee box

Work began renovating the existing greenside bunker on Hole 10. The bunker is being shifted closer to the green and flattened.  Even though the bunker will remain large, it will be reduced by approximately 30%.  Drainage will added to the bottom of the bunker.  

Hole 10 bunker renovation

The front right greenside bunker on Hole 13 was eliminated.  The bunker was filled and the edges were graded to match the surrounding grade. This was seeded and covered.
 

Filled in bunker

The new forward tee on Hole 15 received its final grade and was sodded.

new Hole 15 forward tee

Three bunkers on Hole 18 have been eliminated. The first left fairway bunker was filled.  Extra fill was used on this to create more of a mound feature on the hole. This bunker was seeded and covered. Seed germination has been great and the bunker is mostly covered.

filled in former bunker

The front right greenside bunker on Hole 18 was filled. The bunker edges were graded to match the surrounding grade. This was seeded and covered.  Seed germination has been great and the bunker is mostly covered.

filled in former bunker

The back right greenside bunker on Hole 18 was filled. The bunker edges were graded to match the surrounding grade.  This was seeded and covered.  Seed germination has been great and the bunker is mostly covered.

filled in former bunker

Conservation work continued at Yahara.  A large area to the east of Hole 18 has been cleared of underbrush and has revealed a large oak savannah.  This area will be managed like and oak savannah restoration now with the help of conservation and ecology teams.  

Oak savannah area

Upcoming Work

Complete bunker work on Hole 10

Build new forward tee on Hole 14

Final grading of new approach on Hole 14

Construct new bunker on Hole 18 approach

Construct new bunker on Hole 18 fairway

View past project updates »

Project Details

  • Location

    • 6701 US Highway 12 & 18 East
      Madison, WI 53718
  • Status

    Construction
  • Estimated Schedule

  • Impact

    Major
  • Alder District

    District 16

Project Information

The Master Concept Plan for Yahara Hills is available.

Yahara Hills Golf Course Redesign FAQ

Background

The Task Force on Municipal Golf in Madison Parks was formed in 2019 to provide recommendations to the City related to the Golf Enterprise Program and the land that it currently uses.  The Task Force’s FINAL REPORT was accepted by the Common Council in January 2021.  The report offered ten recommendations, including that the City should continue providing golf services and that it should reduce 18 holes of golf at Yahara Hills. Though the Task Force did recommend against selling of park land to generate reinvestment funding, it did not have the specific proposal related to a sale to Dane County to consider.

In February 2023 the City of Madison closed on the sale of roughly 200 acres of Yahara Hills Golf Course to Dane County, with a visionary plan to develop a Sustainability Campus. This forward-thinking initiative aims to create a vibrant hub for sustainable practices, environmental education, and community engagement. The Sustainability Campus offers benefits to the City such as reduced transportation costs and emissions, increased operational efficiency, localized waste management control, and a heightened awareness of responsible waste practices.  The Sustainability Campus is still in the planning stages, and full implementation will take place over a number of years.  The Golf Program will utilize proceeds from the Land Sale to make investments in the course.   

Meanwhile, 36 holes of golf are still available at the course and the City has entered into an agreement that allows for continued operation of the golf course, with a phased reduction from 36 holes to 18 holes by the end of the 2025 season. Our vision is to optimize the golfing experience for 18 holes while utilizing existing infrastructure and preserving the natural landscape. In addition, one of our key objectives is to make golf more accessible and enjoyable for everyone. To achieve this, we are committed to providing enhanced short tees. These tees will allow beginners, juniors, and those seeking a more relaxed round of golf to have a satisfying experience while still enjoying the challenge of the course. Our approach is intended to minimize disruption to the environment and maintain the course's unique character. We understand the importance of balancing the enjoyment of golf with the preservation of our natural resources, and we are dedicated to achieving this delicate harmony.

Timeline

2023-2024 Seasons: Operate existing 36 holes
2025 Season: Operate up to 27 holes
2026 Season until at least 2043*: Operate 18 holes

Please note: Course improvement work will begin in Fall of 2023 and may temporarily impact the number of holes available for play during this time.

*The Parks Division expects offer recreational amenities at this location beyond 2043. However, the type and location of those amenities will be determined at a future date.

Project Plans

The Master Concept Plan for Yahara Hills is available.

Public Engagement

Plans were posted in the Yahara Hills Golf Course clubhouse to solicit feedback through September 1, 2023. Parks staff held a online information and input session and held public drop-in hours in August of 2023.

Presentation Slides

Project Updates

October 22, 2024 Update

Work began on Hole 10. There will be 3 new tees as part of the new design.  The back 2 tees were moved 50 yards to the east to create a dogleg for the hole and bring the water more into play.  A new forward tee was built approximately 240 yards from the green.

New tee box

Work began renovating the existing greenside bunker on Hole 10. The bunker is being shifted closer to the green and flattened.  Even though the bunker will remain large, it will be reduced by approximately 30%.  Drainage will added to the bottom of the bunker.  

Hole 10 bunker renovation

The front right greenside bunker on Hole 13 was eliminated.  The bunker was filled and the edges were graded to match the surrounding grade. This was seeded and covered.
 

Filled in bunker

The new forward tee on Hole 15 received its final grade and was sodded.

new Hole 15 forward tee

Three bunkers on Hole 18 have been eliminated. The first left fairway bunker was filled.  Extra fill was used on this to create more of a mound feature on the hole. This bunker was seeded and covered. Seed germination has been great and the bunker is mostly covered.

filled in former bunker

The front right greenside bunker on Hole 18 was filled. The bunker edges were graded to match the surrounding grade. This was seeded and covered.  Seed germination has been great and the bunker is mostly covered.

filled in former bunker

The back right greenside bunker on Hole 18 was filled. The bunker edges were graded to match the surrounding grade.  This was seeded and covered.  Seed germination has been great and the bunker is mostly covered.

filled in former bunker

Conservation work continued at Yahara.  A large area to the east of Hole 18 has been cleared of underbrush and has revealed a large oak savannah.  This area will be managed like and oak savannah restoration now with the help of conservation and ecology teams.  

Oak savannah area

Upcoming Work

Complete bunker work on Hole 10

Build new forward tee on Hole 14

Final grading of new approach on Hole 14

Construct new bunker on Hole 18 approach

Construct new bunker on Hole 18 fairway

August 27, 2024 Update

The fairway bunker on Hole 11 has been seeded and covered. Seed germination has already started and is beginning to fill in.

Bunker filled in on Hole 11

The back right greenside bunker on Hole 13 has been seeded and covered. Seed germination has already started and is beginning to fill in.

bunker filled in on Hole 13

The new forward tee on Hole 15 was started. The tee surface received its final grade and will be seeded/sodded. Once grown in the tee will be mowed as part of the fairway.

new forward tee on hole 15

The right greenside bunker on Hole 15 was completed. The bunker was shifted closer to the green and flattened out. Drainage was added to the bottom of the bunker. The bunker faces were sodded and sand was added to the bunker. The remaining disturbed ground was seeded and covered.

right greenside bunker on Hole 15

Work began on renovating the left fairway bunker on Hole 15. The old, contaminated sand in the bunker was removed. Work began to shape the bunker and it has received its rough grade.

Hole 15 fairway bunker

Upcoming Work

Adding sand to Hole 16 fairway bunker

Complete the Hole 15 fairway bunker

Seed/sod the new forward tee on Hole 15

Complete filling the right greenside bunker on Hole 14

August 2, 2024 Update

The new forward tee on Hole 16 was completed. Once grown in, the tee will be mowed as part of the fairway.

Forward tee grass

The Hole 16 left greenside bunker was completed. The bunker was shifted closer to the green and flattened out. Work included adding drainage, sodding the bunker faces, and adding sand.

Hole 16 bunker

Work began on renovating the Hole 16 left fairway bunker. The old, contaminated sand in the bunker had to be removed. The bunker was shaped, graded, and received added drainage.

Hole 16 fairway bunker

The left greenside bunker on Hole 11 has been completed.

Hole 11 bunker

The Hole 11 left fairway bunker was eliminated with help from Parks Construction crews.

Removal of Hole 11 bunker

The back right greenside bunker on Hole 13 was eliminated.

Hole 13 bunker eliminated

Forestry mowing began on the course with help from Parks Conservation crews. Work began between West Hole 3 and East Hole 2. The removal of vegetation in this area will allow the existing West Hole 3 tee box to be used to play towards the East Hole 2 green after the redesign is completed.

vegetation removal

Upcoming Work

Complete Hole 16 fairway bunker

Restore area of eliminated Hole 11 fairway bunker

Restore area of eliminated Hole 13 bunker

Begin reshaping of Hole 15 right greenside bunker and fairway bunker

Build new forward tee on Hole 15

July 12, 2024 Update

The new forward tee on Hole 11 has been completed. The tee surface was graded and sodded. Once grown in, the tee will be mowed as part of the fairway.

Hole 11 forward tee

Bunker work has started on Hole 11. The right greenside bunker was filled and graded. This area will eventually be turned into an approach area. The area was seeded and covered.

Hole 11 greenside bunker filled in

The Hole 11 left greenside bunker is being reshaped and reduced in size as part of the redesign. The portion of the bunker that is being removed has been filled, graded, and seeded. The bunker has its final grade and drainage has been added.

Hole 11 left greenside bunker grading

Work has begun on Hole 16. The new forward tee has been constructed. The tee box has been graded and will receive sod.

Hole 16 forward tee box

Work began on the left greenside bunker on Hole 16. The bunker is being reshaped and reduced in size as part of the redesign. The portion of the bunker that is being removed has been filled and graded.

Hole 16 left greenside bunker

Upcoming Work

Complete Hole 11 left greenside bunker

Seed/Sod new Hole 16 tee box

Complete Hole 16 left greenside bunker

Reshaping of Hole 16 fairway bunker

June 26, 2024 Update

The new forward tee on Hole 12 was completed. The tee surface received its final grade and sod. Once grown in, the tee will be mowed as part of the fairway.

Front tee on Hole 12

The Hole 12 fairway bunker was completed. The banks of the bunker were sodded and the flat areas surrounding the bunker received seed and straw matting. Sand was added to the bunker. The sod has already rooted into the soil and we are already seeing germination from the grass seed.

Hole 12 fairway bunker

The new Hole 12 back tee received its final grade. The tee surface was seeded with a low mow Kentucky Bluegrass. The edges of the new tee box were sodded. 

Hole 12 back tee

After seed and sod has established, work on Hole 12 will be concluded.

Long View of Hole 12

Upcoming Work

Completion of removal of Hole 14 greenside bunker

Seed and sod new approach on Hole 14

Completion of Hole 11 left greenside bunker

Begin construction of new forward tee on Hole 11

Begin removal of left fairway bunker on Hole 11

June 12, 2024 Update

The front right greenside bunker on Hole #11 is being eliminated as part of the redesign. Work began to fill this bunker and grade the area to be turned into part of the approach to create a false front to the right of the green.

Area, previously a bunker, filled with dirt on Hole #11

Work also began on the left greenside bunker on Hole #11. While the bunker will remain, work is being done to add new drainage, grading to create a flat bunker, and a reduction of the overall size. The bunker is also being shifted closer to the approach.

Adding drainage to a bunker

Drainage was added to the inside of the fairway bunker on Hole #12.

Added drainage to bunker

Upcoming Work

Preparation of soil and installation of seed and sod on the new Hole #12 forward tee, new Hole #12 back tee, and the surrounding of the fairway bunker on Hole #12

Adding sand to the Hole #12 fairway bunker

Hole #14 greenside bunker - Final grading and installation of seed and sod

Seed and sod the new Hole #14 approach

Continue grading of the Hole #11 right greenside bunker and left greenside bunker

 

 

 

May 20, 2024 Update

Work continued on Hole 12. The left greenside bunker was completed, with sod installed on the bunker faces and sand added to the bunker. Surrounding disturbed areas were seeded.

Re-constructed bunker

Work began on the new forward tee box on Hole 12. The tee was built into the fairway and roughly graded. Final grading is still to come along with seeding or sod. 

Hole 12 forward tee

Work began on the right side fairway bunker on Hole 12. The redesign plan calls for this bunker to decrease in size and slightly re-shaped. The outlet drain was installed. The current sand in the bunker was removed in order to re-shape. The sides of the bunker will be softened to help create a flat bottom.

Hole 12 right fairway bunker

Work began on the new back tee on Hole 12. The new tee box will be 15 yards further back than the existing tee box. The tee will be slightly more elevated than the current tee. The existing back tee was striped to excavate soil for the new tee box location.

Hole 12 new back tee box

The front left greenside bunker on Hole 14 is to be eliminated as part of the redesign. Work began to fill the bunker. The area will be graded and eventually turned into part of the approach. This will create a false front to the right of the green.

Hole 14 greenside bunker being filled with soil.

With the help of the Parks ecology team, 9 trees were planted between the new Hole 1 and the current West Course Hole 1. The West Course Hole 1 is being eliminated, so the trees were needed to divide the new Hole 1 from potential non-golf uses.

Two newly planted trees in grass area

Upcoming Work

Install seed or sod on the new Hole 12 forward tee

Complete grading of new Hole 12 back tee

Complete grading of Hole 12 fairway bunker

Complete grading of Hole 14 greenside bunker

Seed or sod new approach on Hole 14

May 3, 2024 Update

Completed Work

Work has continued on Hole 17. The final grade on the former right greenside bunker has been set and the area has been seeded, fertilized, and covered with straw matting.

Area, previously a bunker, filled with dirt next to the 17th green

The Hole 17 left greenside bunker faces were softened to create a flat bunker and the overall size of the bunker reduced. Sod was installed on the faces of the bunker and the bunker will be filled with sand.

Reconstruction of left greenside bunker on Hole 17

Work began on the greenside bunkers for Hole 12. The redesign plan called for the back left bunker to be eliminated. The bunker has been filled and the area seeded, fertilized, and covered with straw matting.

Hole 12 greenside bunker being filled with soil

The front left greenside bunker on Hole 12 is being reconstructed. This work includes adding new drainage, grading of the face slopes to create a flat bottom, and reduction to the overall size.

Area, previously a bunker, filled with dirt next to the 12th green

Upcoming Work

Add sand to the bunker on Hole 17

Prep the soil for seed and sod on the front left side bunker on Hole 12

Seed and sod the front left bunker on Hole 12

Begin moving dirt and shaping the fairway bunker on Hole 12           

Begin building the forward tee box on Hole 12

April 18, 2024 Update

Completed Work

Over the last two weeks bunkers on hole number 2 were filled to final grade and seeded. We expect to see germination of the seed within two weeks.

Area, previously a bunker, filled with dirt and seeded

Drainage has been added to the left side of hole number 12 to alleviate wet conditions.

Line of drainage ditch through turf

Bunker work began on hole number 17. The bunker on the right side of the green is being eliminated and is being filled and graded. The left greenside bunker is being re-constructed. That work includes adding new draining, grading of the slope, and reduction of the overall size.

Grading operations of reconstruction of left greenside bunker

Upcoming Work

Complete the removal of bunker on hole number 17.

Prepare the soil for seed and sod on the left side bunker on hole number 17.

Remove (fill) the back left greenside bunker on hole number 12.

Shape the lower face on the greenside bunker on hole number 12.

March 27, 2024 Update
Area, previously a bunker, filled with dirt on #2 fairway
Area, previously a bunker, filled with dirt on #2 fairway
Area of stump grinding and seeding

Construction is underway! Parks will be posting biweekly construction updates throughout the year. Construction work is being completed by Madison Parks Golf staff.

Completed Work

Filled and graded the two fairway bunkers on #2 fairway which were planned for removal.

With a special thanks to the Streets Division, stumps left from tree removals performed during the winter were ground and filled. The areas were seeded and will begin to fill in as soon as warmer weather comes.

Upcoming Work

Soil preparation and seeding of filled bunkers on #2 fairway

Drainage improvements to #12 greenside bunker

Re-shaping of #17 greenside bunker

Re-shaping of #12 greenside bunker

Was this page helpful to you?