Allis/Spaanem/Shaffer Water Main Installation

Project Details

  • Location

    • 4724 Spaanem Ave.
      Madison, WI 53716
  • Status

    Completed
  • Alder District

    District 15

Project Information

Approximate Schedule

Late-August to Mid-October

Water Main Work

A new 12-inch water pipeline will be installed on the north side of Allis Avenue (between Turner Avenue and Shaffer Avenue) and on the east side of Shaffer Avenue. There will also be new pipeline installed through the Allis Avenue and Spaanem Avenue intersection. Several new fire hydrants will be spaced out along this pipeline and installed in the terrace on the same side as the new pipeline. Construction operations may include but not be limited to:

  • Sawing of asphalt pavement

  • Asphalt removal

  • Excavation

  • Water pipeline installation

  • Reconnection of Allis and Shaffer Avenue water services

  • Backfill, soil compaction, and base course placement

  • Paving operations of asphalt

  • General site maintenance, cleanup and restoration

Project Location Map

(Click for larger)

Water Shut-offs

Properties within the project limits and on Spaanem Avenue will experience an average of two water outages as the new water main gets connected to the existing system and water services are connected. Water outages may last up to 8 hours but will typically take less than 4 hours to complete. Properties will be notified at least 48 hours in advance of planned water outages.

Traffic Impacts

The areas where new water pipeline is getting installed will be closed to through traffic until the streets are restored. Driveway access to properties will only be limited during times that work is taking place directly in front of a driveway, otherwise typical access will be coordinated throughout the project.

Bus Routes & Pickup Locations

There are no current bus routes within the project area, and bus routes nearby on Turner Avenue and Buckeye Road are not expected to be altered as a result of this work.

Streets

The street pavement will be removed and replaced where necessary to allow for the pipeline installation.

Project Contacts

Project Manager:

Pete Holmgren

608.261.5530

pholmgren@madisonwater.org

Traffic Engineering:

Tom Mohr

608.267.8725

tmohr@cityofmadison.com

Metro Transit:

Tim Sobota

608.261.4289

tsobota@cityofmadison.com

Construction Contractor:

Dan Brice

S&L Underground

608.513.8673

Construction Inspection:

Brian McNeary

608.209.7116

bmcneary@madisonwater.org

City Engineering:

John Fahrney

608.266.9091

jfahrney@cityofmadison.com

Was this page helpful to you?