Reetz Road and Altem Circle
Project Details
Project Information
Construction Update
Street signs need to be installed then road can be open to all traffic.
Reetz Rd (Freeport – Hammersley) is open to local traffic only.
Project Description
The project consists of resurfacing with new asphalt pavement, and spot replacement of concrete curb and gutter, drive aprons, and sidewalk. Utility replacement will include new storm sewer improvements.
Project Limits
Reetz Road – Raymond Road to Hammersley Road
Altem Circle – Reetz Road to west end
Project Schedule
City Work will begin in late April to Early May and is expect to last for 2-3 months.