South Owen Drive Reconstruction

March 18, 2024 Update

MG&E Gas has begun replacing their private gas main throughout the project area along S. Owen Dr. The existing gas main will be retired and approximately 2,300 feet of new 2-inch gas main will be installed via directional boring on both sides of S. Owen Dr under the sidewalk.  MG&E Gas utility work is expected to be completed by approximately April 18th, 2024.

Additionally, the start date for the City’s reconstruction of S. Owen Dr has been delayed 6-8 weeks due to a sanitary sewer permitting issue.  The project is now anticipated to begin approximately late May/June 2024.  Additional details will be communicated to residents through the project web page and via a “Start of Construction” letter that will be mailed out to residents two weeks prior to the start of construction.

View past project updates »

Project Details

  • Location

    • 46 S Owen Drive
      Madison, WI 53705
  • Status

    Bidding
  • Estimated Schedule

  • Impact

    Major
  • Alder District

    District 5
  • Contract Number

Project Information

Project Overview

The purpose of this project is to reconstruct S. Owen Drive from Hillcrest Drive to Regent Street. Proposed work includes replacement of the asphalt pavement and road base, replacement of the sanitary sewer main and laterals, replacement of the storm sewer and private storm connections, installation of new curb and gutter, and replacement of sidewalk and drive aprons as needed.

Details and fact sheet
Proposed Assessments

Project Limits

S. Owen Drive from Hillcrest Drive to Regent Street

Project Schedule

Design: Fall/Winter 2022
Construction: April 2023
Scheduled Completion: August 2023 (Approximate)

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Survey

Thank you for everyone who completed the survey. The results will help the project manager design and present as the process moves forward.

Public Information Meetings

If you need an interpreter, translator, materials in alternate formats or other accommodations to access this service, activity or program, please call Reid Stiteley of the Engineering Division at (608) 266-4093.

Si necesita un intérprete, un traductor, materiales en formatos alternativos u otros arreglos para acceder a este servicio, actividad o programa, comuníquese inmediatamente al número de teléfono que figura a continuación.

Yog tias koj xav tau ib tug neeg txhais lus, ib tug neeg txhais ntawv, cov ntaub ntawv ua lwm yam los sis lwm cov kev pab kom siv tau qhov kev pab, kev ua num los sis kev pab cuam no, thov hu rau tus xov tooj hauv qab no tam sim no.

City Process, Meetings

Board of Public Works: 11/2/22 - public hearing
Common Council: 11/22/22 - public hearing

Mailing

Board of Public Works Notice Mailing
Common Council Mailing: Hearing Notice; Residential Survey; Assessment 

Project Updates

MG&E Gas has begun replacing their private gas main throughout the project area along S. Owen Dr. The existing gas main will be retired and approximately 2,300 feet of new 2-inch gas main will be installed via directional boring on both sides of S. Owen Dr under the sidewalk.  MG&E Gas utility work is expected to be completed by approximately April 18th, 2024.

Additionally, the start date for the City’s reconstruction of S. Owen Dr has been delayed 6-8 weeks due to a sanitary sewer permitting issue.  The project is now anticipated to begin approximately late May/June 2024.  Additional details will be communicated to residents through the project web page and via a “Start of Construction” letter that will be mailed out to residents two weeks prior to the start of construction.

The S. Owen Drive reconstruction project has been awarded to the low bidder, Speedway Sand & Gravel Inc. Construction for this project is anticipated to begin on April 8th, 2024 and completion is estimated by August 1, 2024. Residents will be sent an informational “Start of Construction” letter in the spring of 2024 which will include the contact information for both the City’s on-site Construction Inspector and Speedway SG’s Construction Manager.

Was this page helpful to you?