Tokay Boulevard Resurfacing
Project Details
Project Information
Latest Update
3/21/2022 Update:
Thank you everyone for attending the March 21, 2022 Public Information Meeting. The March 21, 2022 Public Information Meeting Recording is now available.
March 21, 2022 Public Information Meeting PowerPoint Presentation
Plans and Specifications and authorizing the Board of Public Works to advertise the project will be presented at the April 6, 2022 Board of Public Works meeting.
Project Overview
This is a street resurfacing project with limit sanitary sewer replacement and storm sewer improvements.
Project Overview Plan
View Proposed Assessments
Project Limits
Tokay Boulevard: South Segoe Road to South Whitney Way
Project Schedule
Approving Plans Specifications: April 6, 2022
Bid Advertisement: April 28, 2022
Start of Construction: End of July 2022
End of Construction: October 2022
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
City Process, Meetings
Board of Public Works: April 6, 2022
Common Council: April 19, 2022