Tenney Park Beach Shelter Replacement

October 18, 2024 Update

Quarter 4 Update
The new shelter and restrooms at Tenney Beach is taking form.  The masonry and most of the stone veneer has been completed.  The roof structure is currently being installed and after that is completed the door and storefront frames will be installed.  The project is on track to be completed by the end of the year and will be winterized and opened for public use next spring.

Watch the construction progress of the new beach shelter on the live construction site camera.  A Tenney Park Beach Shelter Flickr album will also highlight progress photos every few weeks.

View past project updates »

Project Details

  • Location

    • 1330 Sherman Ave, Tenney Park
      Madison, WI 53703
  • Status

    Construction
  • Estimated Schedule

  • Impact

    Minor
  • Alder District

    District 6

Project Information

Latest Update

The bid for the project to construct the new beach shelter was opened July 13, 2023 and was awarded through Board of Public Works and Common Council in late July & early August to Tri-North Builders, Inc.  A Start Work letter was issued on August 21, 2023 and the Contractor closed out 2023 with submittals and subcontractor qualifications.  Work is anticipated to begin in April 2024 with the demolition of the existing building and continue through 2024.

Project Overview

Madison Parks, in conjunction with City Engineering-Facilities will be replacing the existing beach shelter at Tenney Park.  A clean beach system was originally intended to be a component of the project, however difficulties in the ongoing operation of the system at Warner Park beach have put that component of the project on indefinite hold.

The beach shelter is proposed to be similar to shelters in Lake Edge ParkEsther Beach ParkOlbrich Park - Walter Street and Warner Park beach.   The beach shelter replacement project was approved as part of the City of Madison's adopted Capital Budget and was originally proposed to be constructed beginning in fall of 2021; however, the delay in delivery of the clean beach system (including the wave impact attenuation system) to Warner Park necessitated holding the project at Tenney Park so that Parks Operations staff would have adequate time to implement and maintain the system prior to its use at other locations.

Proposed Project Schedule

City User Agency: Parks Division

Planning and Design: February - June 2021

1st Advertisement of Bid: June 1, 2023

Bid Due Date: Thursday, July 13, 2023

Construction Start Date: Sept. 2023

Expected Completion Date: Dec. 2024

PLEASE NOTE:  When construction on the project begins, the beach at Tenney may be closed for the duration or a significant portion of the swimming season.  Notice will be posted to this page and to the alder/neighborhood association when definitive construction dates are known.


Background

A public meeting to review and discuss the project was held on February 16, 2021 via Zoom.  At this meeting staff from Parks, Engineering Facilities and consultant Destree Design Architects presented information on the site existing conditions, clean beach treatment system and options for the shelter's color palette.  As part of the discussion, attendees at the session asked for staff to research as a possible color option the original color of the nearby Ferry building (located on the corner of Marston Ave and Sherman Ave). 

Following the meeting, staff enlisted the services of an historic paint investigator who determined that the original color was a dark green referenced by the Tarrytown Green color as currently manufactured by Benjamin Moore.  This information, together with a stone sample (Kasota stone) more closely matching the historic stone on the bridges as shared with attendees and the Tenney Lapham Neighborhood Association, who voted to use both in the design moving forward.  As such, an updated rendering showing the building with these features is included below.


Public Input Meeting #1

Via Zoom 2/16/2021 @6pm

Please note: this meeting was not recorded

For the City of Madison Engineering more information and status updates. 


Project Updates

October 18, 2024 Update

Quarter 4 Update
The new shelter and restrooms at Tenney Beach is taking form.  The masonry and most of the stone veneer has been completed.  The roof structure is currently being installed and after that is completed the door and storefront frames will be installed.  The project is on track to be completed by the end of the year and will be winterized and opened for public use next spring.

Watch the construction progress of the new beach shelter on the live construction site camera.  A Tenney Park Beach Shelter Flickr album will also highlight progress photos every few weeks.

July 12, 2024 Update

The clean beach system will be delayed indefinitely. The Clean Beach System is an innovative solution, and Parks is continuing to work through final design details and daily operations.  We will provide updates when they are available..  

June 21, 2024 Update

Watch the construction progress of the new beach shelter on the live construction site camera!  A Tenney Park Beach Shelter Flickr album will also highlight progress photos every few weeks.  

May 7, 2024 Update

Work is currently underway on the project to replace the beach shelter at Tenney Park!  Please note that during construction, the beach and playground near the shelter (aka "the pirate ship playground") at Tenney will be closed.  Notice will be posted to this page and to the alder/neighborhood association when these amenities are again available for use.

April 10, 2024 Update

Demolition of the existing beach shelter building is scheduled to begin the week of April 22nd and continue for two weeks.  Following the demolition of the building, work will get underway on the utilities and construction of the new shelter building.

Was this page helpful to you?