Solar PV – Fleet Phase 2
Project Details
Project Information
Latest Update
October 04, 2023
Project status: Completed
Project Overview
Installation of a roughly 200 kW solar photovoltaic system at the Fleet Services Main Facility. The system will consist of roof mounted modules and will produce an estimated 250,000 kWh per year. When combined with the building’s existing array, 55% of the building’s electricity usage will be generated by the solar arrays. The array will be installed by the Engineering Division’s GreenPower program where trainees with little to no electrical skills are provide on-the-job training through solar installations on City buildings.
Project Schedule
City User Agency: City of Madison Fleet Services
Design and Planning: Jan – April 2022
1st Advertisement of Bid: N/A
Bid Due Date: N/A
Construction Start Date: April 2022
Expected Completion Date: August 2023