1. Engineering Downtown Offices Closed to Public, Dec. 26 & 27, 2024.

    Offices will be closed, however, City of Madison Engineering Division staff will be available by phone: 608-266-4751 and email: engineering@cityofmadison.com.

Village on Park Improvements

September 30, 2024 Update

Quarter 4 Updates
Phase 1 Parking Structure & Grocery Alteration Work

Below grade foundation work for the parking structure has been completed. The adjacent grocery store alteration work has been completed and the new tenant will begin remodeling work soon. The parking structure floor decks levels 1 through 4 have been constructed. The contractor is currently working on forming the floor for deck level 5. Construction of the vertical floor deck levels will continue into November of this year.  Construction of interior concrete block walls will begin in mid-October on the lower levels. View the progress on time lapse images from the construction site camera.

Phase 2 Central Green Space Site Improvements

The site improvements work for Phase 2 are planned to go out for bidding in February 2025. Construction for the Phase 2 site improvements work will begin in June 2025 or as soon as the parking structure is operational. The parking structure will need to be operational to provide parking for mall tenants and visitors while the central surface parking lot areas and the central green space site improvements are in construction. Construction completion of Phase 2 site improvements work is planned for December 2025.

View past project updates »

Project Details

  • Location

    • 2300 South Park Street
      Madison, WI 53713
  • Project Type

  • Status

    Bidding
  • Estimated Schedule

  • Alder District

    District 14

Project Information

Project Overview

Phase 1 Village on Park Parking Structure and Grocery Alterations Work

Design and construction, including site development, for Phase 1 Village on Park Parking Structure and Grocery Alteration Work located at 808 Hughes Place (Parking Structure) and 2328 South Park Street (Grocery Alteration Work). 

Phase 1 is for the construction of the Parking Structure and Grocery Alteration Work along with limited site work adjacent to the new Parking Structure. The parking structure will have approximately 295 parking stalls above grade with approximately 6-levels. It will operate as a fully automated self-parking structure. The Grocery Alteration Work is for structural roof alteration work and a new storefront entrance door in the adjacent grocery store tenant.

Phase 2 Village on Park Central Green Space Site Improvements

Phase 2 will be for the future Central Green Space Site Improvements that will be a separate project (and separate bid) for construction in 2025 and is not included in the Phase 1 Parking Structure construction project.  The Phase 2 improvements are currently planning for bidding at the end of year 2024 and to start construction as soon as the parking structure is operational in 2025.

Village on Park Site Phasing Plan

Watch the progress on our project Flickr page.  For additional information please see the City of Madison DPCED Planning South Madison Plan

October 31, 2022 Update: On June 8, 2022 the Madison Arts Commission (MAC) selected Michael Ford, also known as the “Hip Hop Architect”, to create the integrated public art component for a new parking structure planned for 2300 South Park Street. Michael Ford has since refined his designs and is seeking public input about his public art and design concepts by November 7 at noon. For more information about this public art component and a link to the survey, please click HERE.  

January 11, 2023 Update: The project is currently in the construction document phase. Recent committee reviews include approval by the Urban Design Commission on December 14, 2022, and approval by the Plan Commission on January 9, 2023 as noted in the City Process Meetings section below.  The Madison Arts Commission approved the public art component at their meeting on December 13, 2022. Also take a look at the updated renderings of the proposed new parking structure further down on this page.

Project Schedule 

Village on Park Parking Structure and Grocery Alterations Work

City User Agency: Community Development Authority

Planning and Design: April 18, 2022 - April 2023

1st Advertisement of Bid: Dec. 07, 2023 RFB #12112-0-2023-JW is available only on VendorNet and Demand Star
Bid Talk via Zoom:
Jan. 04, 2024 Bid Talk: Village on Park Recording     

Pre-Bid Project Tour: UPDATED to Jan. 16, 2024 @ the project site, 2300 South Park St. Madison, WI 
Bid Due Date: January 30, 2024
Construction Start Date: February 2024
Parking Structure Construction Timeline: February 2024 to May 30, 2025
LEED Goals: Parksmart Certification

"All information regarding dates/times are informational and should be verified with official bidding documents."

Public Involvement

City Process Meetings

May 16, 2023 Common Council File #77483
May 03, 2023 Board of Public Works File #77483
Approving plans and specifications for public improvements necessary for the project known as 808 Hughes Place - Village on Park Parking Structure and Site Improvements and authorizing construction to be completed by permit, Private Development File No. 9323

Jan. 09, 2023 File #74543
Plan Commission: Conditional Use approval for a building exceeding five stories and 68 feet in height to allow construction of a six-story private parking garage at the Village on Park.

Dec. 08, 2022 File #75018
Madison Arts Commission: Accepting the proposed public art concepts on the new Village on Park Parking Structure.

Sep. 07, 2021 File #66450
Accepting the parking study and final parking count determination for the Village on Park.

Village on Park Master Site Plan:

VOP_MasterPlan

Proposed Preliminary Parking Structure Renderings

VOP Jan 2023 NE
Village on Park Parking Structure NE Perspective Updated Jan. 2023
VOP Jan 2023 SE
Village on Park Parking Structure SE Perspective Jan. 2023
VOP_SE_PrelRendering
VOP_NE_PrelRendering

In the News

Oct. 27, 2022 City of Madison News
Seeking local input on Michael Ford’s public art and design concepts

Aug. 01, 2022 Wisconsin State Journal
Madison to invest $5 million more at Village on Park mall

Project Updates

September 30, 2024 Update

Quarter 4 Updates
Phase 1 Parking Structure & Grocery Alteration Work

Below grade foundation work for the parking structure has been completed. The adjacent grocery store alteration work has been completed and the new tenant will begin remodeling work soon. The parking structure floor decks levels 1 through 4 have been constructed. The contractor is currently working on forming the floor for deck level 5. Construction of the vertical floor deck levels will continue into November of this year.  Construction of interior concrete block walls will begin in mid-October on the lower levels. View the progress on time lapse images from the construction site camera.

Phase 2 Central Green Space Site Improvements

The site improvements work for Phase 2 are planned to go out for bidding in February 2025. Construction for the Phase 2 site improvements work will begin in June 2025 or as soon as the parking structure is operational. The parking structure will need to be operational to provide parking for mall tenants and visitors while the central surface parking lot areas and the central green space site improvements are in construction. Construction completion of Phase 2 site improvements work is planned for December 2025.

July 2, 2024 Update

Quarter 3 Update
Phase 1 Parking Structure & Grocery Alteration Work

Site demolition work has been completed and the new rammed aggregate piers have been installed. Work that is currently in progress includes excavation and installation of concrete foundations and footings. Steel beams have been installed in the grocery store space that will provide additional support for the existing roof framing for snow load. The storm laterals, water main connection, and sanitary main connections have been completed. A tower crane has been installed that will be used throughout the duration of construction for the floor decks. The new storefront assembly for the grocery store entrance will be installed by mid-July with occupancy approval by the end of July. Footings and foundation work is nearing completion. The next steps will be to pour the slab-on-grade concrete floor slabs. Then once the slab-on-grade work is completed then begin working on the formwork and post-tensioned concrete floor slabs for each of the vertical floor levels. Construction of the vertical floor levels will continue through November of this year.  View the progress on time lapse images from the construction site camera.

Phase 2 Central Green Space Site Improvements

The site improvements work for Phase 2 are planned to go out for bidding later this year. Construction for the Phase 2 site improvements work will begin around June 2025 or after the parking structure is operational. The parking structure will need to be operational to provide parking for mall tenants and visitors while the central surface parking lot areas and the central green space site improvements are in construction. 

May 28, 2024 Update

Site work has begun for the ramp.  View the progress on time lapse images on the construction site camera.

April 1, 2024 Update

Qtr. 2 update
The construction contract has been approved and issued to Findorff. Building permits have been issued and jobsite setup is currently in progress. The first part of the project is to install new roof beams in the adjoining grocery store space that will provide additional snow load capacity. As well as ordering and installing the new storefront assembly for the grocery store space that will be installed in June. Other work in progress is foundations excavation for the parking structure and installation of the rammed aggregate pier footing supports beginning in April. The below grade foundations installation work is planned for completion in June. Slab-on-grade floors are planned to be installed in June and July. The above grade parking deck levels will begin construction after the first floor slab is completed. Construction of all of the parking deck levels are planned for completion around October/November of this year. Completion of construction is planned for May 2025.

February 2, 2024 Update

The bid due date for Village on Park Phase 1 was on Tuesday, January 30, 2024.  The project received three bids. The low bidder for this project is Findorff. The bid tabulation and summary is available at 

The bid results are also available on VendorNet or Demand Star.

January 22, 2024 Update

Addendum #3 for this project was issued today, January 22, 2024.  As part of that addendum, the bid due date has been extended to Tuesday, January 30, 2024.  Please see the official bid documents on VendorNet or Demand Star for additional information.

January 8, 2024 Update

NOTICE!
The Project Tour that was scheduled on January 9th has been canceled due to poor weather conditions with possible heavy snow that is forecasted in Madison, WI for tomorrow.  The Project Tour has been rescheduled for Tuesday, January 16, 2024 at 10:30 a.m. at 2300 South Park St.  Please meet in the Atrium Lobby.  This meeting is optional.

A virtual Bid Talk was held on Thursday, Jan. 04, 2023.  A link to the recording and presentation slides are available at Jan. 04, 2024 Bid Talk: Village on Park Recording and 

 

January 2, 2024 Update

A reminder to join our Bid Talk via Zoom: Jan. 04, 2024 @ 11:00 a.m. Pre-registration is required at Bid Talk: Jan. 04, 2024 Village on Park Registration

The City of Madison Engineering Division is hosting a virtual live (and later recording posted) sessions called “Bid Talks.” This is an opportunity for you to learn about the project to help with your bid and estimating numbers. During our “Bid Talks” session for this project, the project staff will present information about the project specific to your bidding process. Staff will answer any questions you have. You will also be able to see who is attending. This meeting will be held in a more informal format, where you’ll be able to ask questions and have a conversation. Please send your estimators and bidders to these Bid Talks. Registration prior is required.  A recording link will also be posted to the project page after the meeting.

 

December 11, 2023 Update

The Project Overview has been updated, including this Village on Park Site Phasing Plans showing the phasing of this project.  

This project is for the design and construction, including site development, for Phase 1 Village on Park Parking Structure and Grocery Alteration Work located at 808 Hughes Place (Parking Structure) and 2328 South Park Street (Grocery Alteration Work). 

Phase 1 is for the construction of the Parking Structure and Grocery Alteration Work along with limited site work adjacent to the new Parking Structure. The parking structure will have approximately 295 parking stalls above grade with approximately 6-levels. It will operate as a fully automated self-parking structure. The Grocery Alteration Work is for structural roof alteration work and a new storefront entrance door in the adjacent grocery store tenant.

Phase 2 will be for the future Central Green Space Site Improvements that will be a separate project (and separate bid) for construction in 2025 and is not included in the Phase 1 Parking Structure construction project.

 

 

 

 

December 8, 2023 Update

The City of Madison Engineering Division is hosting a virtual live (and later recording posted) sessions called “Bid Talks.” This is an opportunity for you to learn about the project to help with your bid and estimating numbers. During our “Bid Talks” session for this project, the project staff will present information about the project specific to your bidding process. Staff will answer any questions you have. You will also be able to see who is attending. This meeting will be held in a more informal format, where you’ll be able to ask questions and have a conversation. Please send your estimators and bidders to these Bid Talks. Registration prior is required.  A recording link will also be posted to the project page after the meeting.

Bid Talk via Zoom: Jan. 04, 2024 @ 11:00 a.m. Pre-registration is required:                   Bid Talk: Jan. 04, 2024 Village on Park Registration

December 7, 2023 Update

Project Status updated to BIDDING!

Please see the "Project Schedule" below for informational dates and links.

October 2, 2023 Update

Bid due date was on August 31, 2023. Two bids were received. Based on the bids received, both were above the estimate. The Community Development Authority of the City of Madison has decided that neither vendor will be awarded this RFB at this time. The project will be re-bid with two separate bid packages, one for the Parking Structure and re-aligned drive area, and the other bid package will be for the site improvements only for the central green space and central parking lot area.  Please see the updated Project Schedule.

Was this page helpful to you?