Village on Park Improvements
September 30, 2024 Update
Quarter 4 Updates
Phase 1 Parking Structure & Grocery Alteration Work
Below grade foundation work for the parking structure has been completed. The adjacent grocery store alteration work has been completed and the new tenant will begin remodeling work soon. The parking structure floor decks levels 1 through 4 have been constructed. The contractor is currently working on forming the floor for deck level 5. Construction of the vertical floor deck levels will continue into November of this year. Construction of interior concrete block walls will begin in mid-October on the lower levels. View the progress on time lapse images from the construction site camera.
Phase 2 Central Green Space Site Improvements
The site improvements work for Phase 2 are planned to go out for bidding in February 2025. Construction for the Phase 2 site improvements work will begin in June 2025 or as soon as the parking structure is operational. The parking structure will need to be operational to provide parking for mall tenants and visitors while the central surface parking lot areas and the central green space site improvements are in construction. Construction completion of Phase 2 site improvements work is planned for December 2025.
View past project updates »Project Details
Project Information
Project Overview
Phase 1 Village on Park Parking Structure and Grocery Alterations Work
Design and construction, including site development, for Phase 1 Village on Park Parking Structure and Grocery Alteration Work located at 808 Hughes Place (Parking Structure) and 2328 South Park Street (Grocery Alteration Work).
Phase 1 is for the construction of the Parking Structure and Grocery Alteration Work along with limited site work adjacent to the new Parking Structure. The parking structure will have approximately 295 parking stalls above grade with approximately 6-levels. It will operate as a fully automated self-parking structure. The Grocery Alteration Work is for structural roof alteration work and a new storefront entrance door in the adjacent grocery store tenant.
Phase 2 Village on Park Central Green Space Site Improvements
Phase 2 will be for the future Central Green Space Site Improvements that will be a separate project (and separate bid) for construction in 2025 and is not included in the Phase 1 Parking Structure construction project. The Phase 2 improvements are currently planning for bidding at the end of year 2024 and to start construction as soon as the parking structure is operational in 2025.
Village on Park Site Phasing Plan
Watch the progress on our project Flickr page. For additional information please see the City of Madison DPCED Planning South Madison Plan
October 31, 2022 Update: On June 8, 2022 the Madison Arts Commission (MAC) selected Michael Ford, also known as the “Hip Hop Architect”, to create the integrated public art component for a new parking structure planned for 2300 South Park Street. Michael Ford has since refined his designs and is seeking public input about his public art and design concepts by November 7 at noon. For more information about this public art component and a link to the survey, please click HERE.
January 11, 2023 Update: The project is currently in the construction document phase. Recent committee reviews include approval by the Urban Design Commission on December 14, 2022, and approval by the Plan Commission on January 9, 2023 as noted in the City Process Meetings section below. The Madison Arts Commission approved the public art component at their meeting on December 13, 2022. Also take a look at the updated renderings of the proposed new parking structure further down on this page.
Project Schedule
Village on Park Parking Structure and Grocery Alterations Work
City User Agency: Community Development Authority
Planning and Design: April 18, 2022 - April 2023
1st Advertisement of Bid: Dec. 07, 2023 RFB #12112-0-2023-JW is available only on VendorNet and Demand Star
Bid Talk via Zoom:
Jan. 04, 2024 Bid Talk: Village on Park Recording
Pre-Bid Project Tour: UPDATED to Jan. 16, 2024 @ the project site, 2300 South Park St. Madison, WI
Bid Due Date: January 30, 2024
Construction Start Date: February 2024
Parking Structure Construction Timeline: February 2024 to May 30, 2025
LEED Goals: Parksmart Certification
"All information regarding dates/times are informational and should be verified with official bidding documents."
Public Involvement
City Process Meetings
May 16, 2023 Common Council File #77483
May 03, 2023 Board of Public Works File #77483
Approving plans and specifications for public improvements necessary for the project known as 808 Hughes Place - Village on Park Parking Structure and Site Improvements and authorizing construction to be completed by permit, Private Development File No. 9323
Jan. 09, 2023 File #74543
Plan Commission: Conditional Use approval for a building exceeding five stories and 68 feet in height to allow construction of a six-story private parking garage at the Village on Park.
Dec. 08, 2022 File #75018
Madison Arts Commission: Accepting the proposed public art concepts on the new Village on Park Parking Structure.
Sep. 07, 2021 File #66450
Accepting the parking study and final parking count determination for the Village on Park.
Village on Park Master Site Plan:
Proposed Preliminary Parking Structure Renderings
In the News
Oct. 27, 2022 City of Madison News
Seeking local input on Michael Ford’s public art and design concepts
Aug. 01, 2022 Wisconsin State Journal
Madison to invest $5 million more at Village on Park mall