Schmitt Place Reconstruction
March 19, 2024 Update
Construction on Schmitt Place and Harvey Street is scheduled to begin the week of March 25, 2023. The City has awarded the contract for this work to S&L Underground Inc.
View past project updates »Project Details
Project Information
Project Overview
The City Plans to reconstruction Schmidt Place from University Avenue to Harvey Street and Harvey Street from Ridge Street to Schmitt Place. The project will include new asphalt pavement, curb and gutter, driveway aprons and new sidewalk. The project will also include the replacement of the underground utilities which will replace aging sanitary sewer & water main and make storm sewer improvements. New 5-ft sidewalk is proposed on the north-side of Harvey Street from Ridge Street to N Blackhawk Avenue with varying grass terrace widths between the sidewalk and the street to preserve as many existing terrace trees as possible.
Project Limits
Harvey Street: Ridge Street to Schmitt Place Street reconstruction with underground utility replacement and storm sewer upgrades.
Schmitt Place from University Avenue to Harvey Street reconstruction with underground utility replacement and storm sewer upgrades.
Harvey Street: Schmitt Place to Blackhawk Avenue new 5-ft sidewalk installed on the north side of the street.
Project Schedule
Approving Plans Specifications: March 22, 2023
Bid Advertisement: Spring 2024
Start of Construction: Spring 2024
End of Construction: Summer 2024
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
- Oct. 4, 2023 Public Information Meeting Recording
- Oct. 4, 2023 Public Information Meeting PowerPoint Presentation
- March 6, 2023 Public Information Meeting PowerPoint Presentation
- March 6, 2023 Public Information Meeting Recording
- Plan Overview
If you need an interpreter, translator, materials in alternate formats or other accommodations to access this service, activity or program, please email Steve Sonntag, ssonntag@cityofmadison.com of the Engineering Division.
Si necesita un intérprete, un traductor, materiales en formatos alternativos u otros arreglos para acceder a este servicio, actividad o programa, comuníquese inmediatamente al número de teléfono que figura a continuación.
Yog tias koj xav tau ib tug neeg txhais lus, ib tug neeg txhais ntawv, cov ntaub ntawv ua lwm yam los sis lwm cov kev pab kom siv tau qhov kev pab, kev ua num los sis kev pab cuam no, thov hu rau tus xov tooj hauv qab no tam sim no.
City Meetings, Process
Board of Public Works: March 22, 2023
Common Council: April 18, 2023
Transportation Commission: October 11, 2023
Board of Public Works: October 18, 2023
Mailings
Board of Public Works Notice Mailing: Cover Letter, Fact Sheet, Meeting Notice, Assessments
Common Council Notice Mailing: Cover Letter, Meeting Notice, Revised Assessments
Start work letter to residents: Letter and Fact and Detail Sheet
Adopted Resolution Notice: Cover Letter, Finance Letter, Resolution