Starker Avenue Resurfacing with Utilities
April 23, 2025 Update
Construction along Starker Avenue continues from National Avenue to Droster Road. Sanitary sewer installation will be completed the week of April 21. Water main installation will start the week of April 28 and 1-2 weeks. Following water main installation, the Contractor will install storm sewer and as well as start grading operations in preparation for concrete curb and gutter. After the curb and gutter as well as gravel base course is placed, the Contractor will continue on the next phase on other blocks with sanitary sewer installation. The work is on schedule to be completed the end of August 2025. MG&E continues their work replacing gas main within the project limits and is anticipated to be complete by early May 2025. The Construction Inspector, Paul Lauby, 608-520-2378, plauby@cityofmadison.com will be the best on-site contact throughout construction.
View past project updates »Project Details
Project Information
Project Overview
The City is planning to resurface Starker Avenue from Woodvale Drive to Droster Road. The project includes replacing the sanitary sewer and laterals, water main, storm sewer main and inlets, full removal and replacement of the gravel base and asphalt pavement. The project also includes spot replacing driveway aprons, curb and gutter, sidewalk, improving pedestrian crossings, and installing traffic circles at the intersection of Starker Avenue and Woodvale Drive and Starker Avenue and Ellen Avenue.
Project Limits
Starker Avenue from Woodvale Drive to Droster Road
Project Schedule
Assessments to be Mailed: Feb. 23, 2024
Board of Public Works: March 6, 2024
Board of Public Works Approval: April 3, 2024
Common Council Approval: April 16, 2024
Bid Open Date: Fall 2024
Construction: April - August 2025
Public Involvement
There are a number of points of contact during this project where the public was encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
City Process, Meetings
Common Council: April 16, 2024
Board of Public Works: March 6, 2024
Mailings
Board of Public Works: March 6, 2024 Notice of Meeting Fact and Details Sheet Schedule of Assessments