Olin-Turville Ct and E. Lakeside Street Resurfacing

October 1, 2024 Update

The contractor has completed street resurfacing and utility work for the southern half of the project on Olin-Turville Ct between the Olin Park boat launch parking lot and the Olin-Turville Ct/John Nolen Dr intersection.  They are now continuing street resurfacing and utility work on the northern half of the project on Olin-Turville Ct and E. Lakeside St between the Olin Park boat launch and E. Lakeside St/John Nolen Dr intersection. 

The contractor will be paving the northern half of the project next week Tuesday, October, 8th.  Access will continue to be maintained to properties and MSCR facilities on E. Lakeside St throughout paving, but some minor delay should be expected as crews work in this area.  Access to the Olin Park boat launch parking lot will remain from the southern Olin-Turville Ct/John Nolen Dr intersection.  After paving is complete, the contractor will be installing pavement markings and completing site restoration.

View past project updates »

Project Details

  • Location

    • 310 E Lakeside St
      Madison, WI 53715
  • Status

    In Design
  • Estimated Schedule

  • Impact

    Major
  • Alder District

    District 13
    District 14
  • Contract Number

Project Information

Project Overview

The purpose of this street project is to resurface the pavement and replace some underground utilities on Olin-Turville Ct from John Nolen Dr to E. Lakeside St and E. Lakeside St from John Nolen Dr to Olin-Turville Ct.  Work includes replacing approximately 0.41-miles of asphalt pavement, replacing concrete curb and gutter, sidewalk, and curb ramps as needed, replacing sanitary sewer main as needed, and storm culvert replacements.  The existing street widths on all streets will remain the same.

Project Limits

Olin-Turville Ct from John Nolen Dr to E. Lakeside St

E. Lakeside St from John Nolen Dr to Olin-Turville Ct

Project Schedule

Design: Spring/Summer 2024

Anticipated Start of Construction: September 2024

Anticipated End of Construction: October 2024

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Public Information Meetings

June 3, 2024 Public Information Meeting PowerPoint Presentation

June 3, 2024 Public Information Meeting Recording

City Process, Meetings

Common Council: 6/4/2024

Board of Public Works: 5/22/2024

Project Updates

October 1, 2024 Update

The contractor has completed street resurfacing and utility work for the southern half of the project on Olin-Turville Ct between the Olin Park boat launch parking lot and the Olin-Turville Ct/John Nolen Dr intersection.  They are now continuing street resurfacing and utility work on the northern half of the project on Olin-Turville Ct and E. Lakeside St between the Olin Park boat launch and E. Lakeside St/John Nolen Dr intersection. 

The contractor will be paving the northern half of the project next week Tuesday, October, 8th.  Access will continue to be maintained to properties and MSCR facilities on E. Lakeside St throughout paving, but some minor delay should be expected as crews work in this area.  Access to the Olin Park boat launch parking lot will remain from the southern Olin-Turville Ct/John Nolen Dr intersection.  After paving is complete, the contractor will be installing pavement markings and completing site restoration.

September 6, 2024 Update

Starting Monday 9/9, the project contractor will mobilize on site to begin installation of project traffic control and temporary bike paths for pedestrian detour routes.  That same Monday night (9/9), starting at 6:30pm, the contractor will also be installing traffic control and temporary concrete barrier for the pedestrian detour route on John Nolen Drive and this night work will take approximately 7 hours to complete.  Please see previous press release here for more information: https://www.cityofmadison.com/news/2024-08-30/olin-turville-ct-and-e-lakeside-st-resurfacing-project

Following initial traffic control set up, resurfacing and utility work will begin on Olin-Turville Ct for the southern half of the project between the Olin Park boat launch and the southern intersection (Olin-Turville at John Nolen).  This work will take approximately 3-4 weeks to complete.  During this phase, access to properties on E. Lakeside St and the Olin Boat launch will be maintained via the northern intersection at E. Lakeside at John Nolen.

June 3, 2024 Update

Thank you everyone who attended the June 3, 2024 Public Information Meeting. The meeting materials are now available: 

June 3, 2024 Public Information Meeting PowerPoint Presentation

June 3, 2024 Public Information Meeting Recording

May 23, 2024 Update

A public information meeting is scheduled for 5:30 p.m., June 3, 2024, via Zoom. Registration prior is required. 

June 3, 2024 Public Information Meeting Registration 

If you need an interpreter, translator, materials in alternate formats or other accommodations to access this service, activity or program, please email Reid Stiteley, rstiteley@cityofmadison.com 

Si necesita un intérprete, un traductor, materiales en formatos alternativos u otros arreglospara acceder a este servicio, actividad o programa, comuníquese inmediatamente al número de teléfono que figura a continuación.

Yog tias koj xav tau ib tug neeg txhais lus, ib tug neeg txhais ntawv, cov ntaub ntawv ua lwm yam los sis lwm cov kev pab kom siv tau qhov kev pab, kev ua num los sis kev pab cuam no, thov hu rau tus xov tooj hauv qab no tam sim no.

May 8, 2024 Update

This page has been created. Check back for updates and to sign up for the email list.

Was this page helpful to you?