1. Resources for the Madison Community

    Madison stands with the families of Abundant Life community. This page is dedicated to connecting victims and the broader community to resources and accurate information about the tragic events that happened on December 16.

Penn Park Courts Reconstruction

June 6, 2024 Update

The courts will be temporarily closed from June 6 - June 13. The contractor will be installing the acrylic surfacing and the final court striping. Exact work times will be weather dependent. The applied products are applied wet, similar to paint, and require time to dry. Please stay off the courts during this time.

View past project updates »

Project Details

  • Location

    • 2101 Fisher St.
      Madison, WI 53713
  • Status

    Completed
  • Estimated Schedule

  • Impact

    Minor
  • Alder District

    District 14

Project Information

The project area is located in the southwest corner of Penn Park.

View the current plan!

Project Background

The reconstruction of the courts located in the southwest corner of Penn Park has been included in the Parks Division's Capital Improvement Projects budget for 2023. The existing courts (two basketball, one tennis) are in poor condition and require full reconstruction. The two existing basketball courts are planned to be replaced, while the tennis court is planned to be removed and turned into a soccer mini-pitch/futsal court. A mini-pitch is soccer, typically with 5 players per team, played on a small hard court. Futsal is a soccer-based game played on the same court with a smaller, low bounce ball.

Project Planning will began in winter of 2022-2023. Construction is anticipated to begin in fall 2023 with anticipated completion in June 2024. 

Public Input Opportunities

Online Input Meeting

Tuesday, December 20, 2022 at 6:00 pm via Zoom
Presentation Slides
Schematic Plan

In-Person Drop-In Hours

  • Thursday, January 5, 2023 from 4:00 pm - 7:00 pm
  • Friday, January 6, 2023 from 2:00 pm - 5:00 pm

Goodman South Madison Library
2222 S Park St.
Madison, WI 53713

Parks staff was available to inform residents of the project and receive input.

Project Updates

June 6, 2024 Update

The courts will be temporarily closed from June 6 - June 13. The contractor will be installing the acrylic surfacing and the final court striping. Exact work times will be weather dependent. The applied products are applied wet, similar to paint, and require time to dry. Please stay off the courts during this time.

December 20, 2023 Update

The lighting system has been installed and will be functional after MG&E installs the new electrical service. The courts are currently available for play.

Was this page helpful to you?