The following timeline lists the actions/activities to implement the Judge Doyle Square development plan:

City Financial Participation, Land Use Approvals

  • Development Agreement to Common Council - July 5, 2016
  • Sign Development Agreement - July 15, 2016
  • 2017 Executive Capital Budget to Council - Sept 6, 2016
  • Board of Estimates Action on Capital Budget - Sept 26, 2016
  • Final 2017 Capital Budget Adopted by Council - Nov 14-15, 2016
  • Land Use and CSM Approvals/Recordings/Permits - By May 1, 2017
  • Public Development Commencement Closing - May, 2017

TID #25 Project Plan Amendment

  • Letter to Overlying Taxing JurisdictioN - July 25, 2016
  • Introduce Resolution to Common Council - August 2. 2016
  • Organizational Joint Review Board Meeting - August, 2016
  • Plan Commission Public Hearing and Action - August 29, 2016
  • Board of Estimates Action - September 12, 2016
  • Common Council Action - September 20, 2016
  • Joint Review Board Action - Early Oct, 2016
  • Documentation to DOR (deadline) - October 31, 2016
  • DOR approval of Project Plan Amendment - First Quarter 2017

Public Ramp Construction

  • Design, Bid and Award Public Ramp Construction - July 2016 - September 17
  • Demolition of MMB Annex - By May 1, 2017
  • Complete Construction of Block 88 Public Ramp - June 2020
  • Complete Demolition of Government East Garage on Block 105 - February 2021

Private Development

  • By Contract, Commence Block 88 Apartment Element - July 2020
  • By Contract, Commence Block 105 Hotel Element - December 2021
  • By Contract, Commence 2nd Block 105 Private Development Elements - December 2022