Hancock Street, N.
Project Details
Project Information
Project Update
Project Complete
Bike route is maintained on Mifflin.
Project Description
This project will remove and replace concrete curb and gutter; remove and replace sidewalk, as needed; remove and replace drive aprons, install a new asphalt pavement; replace sanitary sewer main and laterals; replace the water main; replace or extend storm sewer, as necessary. During construction, local access will be maintained from at least one end of Hancock Street. Residents will be provided with at least 48 hours' notice if changes to access are proposed.
Project Limits
E Washington Avenue to E Johnson Street
Project Schedule
July 27, 2017 - Public Information Meeting
August 23, 2017 - Board of Public Works
September 5, 2017 - Common Council
April 2, 2018 - Begin Construction
Public Information Meeting
A Public Information Meeting was held on July 27, 2017. The plan from this meeting can be found here: PIM Display