March 18, 2025 Update
The design team has completed 60% design and is working toward a 75% design and utility coordination in the of spring 2025. The Transportation Commission, Board of Public Works, and Common Council approved the geometry for the project on February 19, 2025, March 26, 2025, and March 11, 2025, respectively. The Environmental Document has been approved. The Design Study Report and Traffic Management Plan approval is pending. Soil borings within the street have completed. The design is working on the Transportation Project Plat for the north drainageway along S. High Point Road. The Plat will seek Board of Public Works and Common Council approval in April 2025. The final design and Contractor bidding will be completed in Fall of 2025. Construction is scheduled spring of 2026 through mid-summer 2027.
View past project updates »Project Details
Project Information
Project Overview
Mineral Point Road consists of reconstructing the concrete pavement and base course from the eastern Beltline Ramps to S. High Point Road. The project will include spot replacements of the existing curb and gutter and sidewalk. Improvements includes safety enhancements at Tree Lane/Big Sky Drive and S. High Point Road intersections. There will be a large box culvert installation on Mineral Point Road from Commerce Drive to S. High Point Road and S. High Point Road to the north Greenway Drainage Property. The pavement will be replaced on Mineral Point Road from Commerce Drive to the eastern Beltline Ramps and on S. High Point Road from Mineral Point Road to the north Greenway Drainage Property. Existing street lighting will be reviewed during the design phase for potential replacement. The shared-use path along the north side of Mineral Point Road will remain as well as the BRT station on the east side of the S. High Point Intersection.
Project Limits
Mineral Point Road - Commerce Drive to S. High Point Road
S. High Point Road - Mineral Point Road to North Greenway Drainage Property
Project Schedule
Preliminary Design: 2020-2021, 2024
Final Design: 2025
Construction: 2026
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:
Public Information Meetings
FOR BUSINESS OWNERS and TENANTS:
Nov. 6, 2024 Public Information Meeting Recording (Business Owners and Tenants)
Nov. 6, 2024 Public Information Meeting Presentation (Business Owners and Tenants)
FOR AREA RESIDENTS:
Nov. 6, 2024 Public Information Meeting Recording (Area Residents)
Nov. 6, 2024 Public Information Meeting Presentation (Area Residents)
City Meetings, Process
Board of Public Works: Information will be posted when available.
Common Council: Information will be posted when available.