Sidewalk Replacement Program
March 28, 2025 Update
Thank you to everyone who attended the March 27, 2025 Public Information Meeting. The meeting materials are now available:
- March 27, 2025 Public Information Meeting Recording (District 20)
- March 27, 2025 Public Information Meeting PowerPoint Presentation (District 20)
- District 20 Final Map
Project Details
Project Information
Project Overview
The Annual Sidewalk Replacement Program was created to identify and repair defects (cracks, broken sections, offsets creating trip hazards, ponding/icing issues) throughout the City, rotating through the alder districts on a 10-year cycle.
In 2025, the Sidewalk Replacement Program will be performing work within Aldermanic Districts 10 and 20.
Sidewalk sections marked with white arrows or X’s are designated for replacement. Sidewalk sections with tripping hazards, marked with a pink line across the joint and a white ‘C’, are designated for saw cutting. Separate contracts are bid for the replacement and the saw cutting.
- Criteria for Replacement of Public Sidewalk and Curb and Gutter
- Care and Restoration of Disturbed Turf Areas - Brochure
- Street Assessment Policy
- ADA Ramp Replacement Guidelines
Project Limits
Each cycle focuses on different districts. In 2025, sidewalk sections will be repaired and replaced throughout Aldermanic Districts 10 & 20.
Project Schedule
- District 10: 05/05/2025 to 09/26/2025
- District 20: 04/07/2025 to 09/12/2025
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
- March 27, 2025 Public Information Meeting Recording (District 20)
- March 27, 2025 Public Information Meeting PowerPoint Presentation (District 20)
City Process, Meetings
- Common Council: District 10 – 03/25/2025, District 20 – 03/11/2025
- Board of Public Works: District 10 – 03/12/2025, District 20 – 02/26/2025
Sidewalk Repair Schedule by Alder District
Year | Alder District & Ward |
---|---|
2017 | Districts 15 & 17 |
2018 | Districts 3 & 16 |
2019 | Districts 1, 7 & 9 |
2020 | Districts 4 & 8 |
2021 | Districts 13 & 14 District 14:
District 13: |
2022 | District 5 |
2023 | Districts 12 & 18 |
2024 | District 11 & 19 |
2025 | District 10 & 20
|
2026 | District 2 & 6 |
2027 | District 3 & 17 |
2028 | District 15 & 16 |
2029 | District 1 & 9 |
2030 | District 4 & 13 (Census) |
2031 | District 5 & 8 |
2032 | District 7 & 20 |
2033 | District 10 & 14 |
2034 | District 12 & 18 |
2035 | District 11 & 19 |
2036 | District 2 & 6 |
2037 | District 3 & 17 |
2038 | District 15 & 16 |
2039 | District 1 & 9 |
2040 | District 4 & 13 (Census) |
2041 | District 5 & 8 |
Forms
List of Prequalified Contractors
Related Ordinances, Statutes, & Administrative Procedures
- Madison General Code of Ordinances:
Sidewalks addressed by Section 10.06 & 10.09 - Wisconsin Statutes - Sidewalks addressed by Section 66.0907, Wisconsin State Legislature
- Street Patching Criteria
- Terrace Treatment Policy