Sidewalk Replacement Program

Last Updated: 06/02/2020

Updates

District 1 &7: Sidewalk Replacement complete

District 9: Sidewalk replacement completion expected June 26

District 4 & 8:  Currently working in district 4.  Work in district 8 will begin after district 4 is completed.  All work in district 4 & 8 will be completed by September 25.

General Information

Sidewalk Repair Schedule by Aldermanic District

Year Aldermanic District & Ward
2017 Districts 15 & 17
2018 Districts 3 & 16
2019

Districts 1, 7 & 9

Map of District 1

District 1 Estimated Sidewalk Costs for Properties

Map of District 7

District 7 Estimated Sidewalk Costs for Properties

Map of District 9

District 9 Estimated Sidewalk Costs for Properties

2020

Districts 4 & 8

Map of District 4

District 4 Estimated Sidewalk Costs for Properties

Map of District 8

District 8 Estimated Sidewalk Costs for Properties

2021 Districts 13 & 14
2022 District 5
2023 Districts 12 & 18
2024 District 11 & 19
2025 District 10 & 20
2026 District 2 & 6
2027 District 15 & 17

Forms

List of Prequalified Contractors

Related Ordinances, Statutes, & Administrative Procedures