E Wilson Street and E Doty Street Reconstruction
March 25, 2025 Update
The City’s Contractor (RG Huston) will be re-starting work on E Wilson St (S Pinckney to S Blair St) starting Wednesday, April 2nd following election day. The work is expected to last until mid-June. Due to the depth and complicated installation methods for underground sewer work, the 100 Block of E Wilson St (S Pinckney St to King St) will be fully closed to thru-traffic for an anticipated 2 months starting on Wednesday, April 2nd. Local access will be maintained on this block for both vehicles and pedestrians, however, access will be limited during working hours from one end of the block or the other. A vehicle detour route (for general traffic and Metro buses) will be setup using King St to S Pinckney St, with an all-way stop added at the Pinckney-Doty intersection. An overview of the detour route is included below.
In addition, starting Wednesday April 2nd, the City’s Contractor will close the 100 block of Martin Luther King Jr Blvd at Doty Street to repair concrete pavement within the intersection. The street is anticipated to reopen the following Wednesday, April 9th. See attached map for the approximate work zone limits. The crosswalk on the north leg, crossing MLK Jr Blvd will be closed during this time. Sidewalks will remain open.
General Detour
MLK-Doty Concrete Pavement Document
View past project updates »
Project Details
Project Information
Project Overview
The City is planning the reconstruction of E Wilson St from MLK Blvd to S Franklin St and E Doty St from MLK Blvd to King St in 2024. The project improvements include replacement of existing pavement and pavement base, curb and gutter, sanitary sewer main and laterals, storm sewer, and porting of the water main. Damaged sections of sidewalk will also be replaced or as needed to install sewer service laterals. In addition, a new cycle track will be installed along E Wilson St as part of this project.
Project Limits
E Wilson St – Martin Luther King Jr Blvd to S Franklin St
E Doty St - Martin Luther King Jr Blvd to King St
Project Schedule
Start of Construction – April 2024 (tentative)
End of Construction – October 2024 (tentative)
Business Resources
City's Road Reconstruction Business Guide
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
A public information meeting was held on Dec. 7, 2023. Thank you to all who attended. Materials presented at the meeting, along with a video recording of the meeting may be accessed under project updates.
City Process, Meetings
Common Council: 01/ 23/ 2024 (Tentative)
Board of Public Works: 01/ 10/ 2024
Mailings
Board of Public Works Public Hearing (July 10, 2024): Schedule of Assessments
Letter to property owners, Fact and Detail Sheet, Assessments (Dec. 26, 2023)
Common Council Public Hearing January 24, 2024: Public Hearing Notice, Assessments
Start of Construction Mailing: Fact and Details Sheet