E Wilson Street and E Doty Street Reconstruction
April 10, 2025 Update
The City’s Contractor (RG Huston) has completed the sanitary main installation on the 100 Block of E Wilson St (S Pinckney St to King St), and began working on the sanitary laterals Thursday, April 9. There are three sanitary laterals to be replaced on this block, beginning with the lateral closest to King St (labeled Sanitary Lateral 3 in the Wilson PDF below) and working up the block towards Pinckney. It is anticipated that each lateral will take 1-2 days to complete. The lateral work will require a large excavated trench across Wilson St that will impede both pedestrian and vehicle access, therefore access to individual businesses/properties on the 100 Block of E Wilson St may have to come from S Pinckney St or from King St, depending on where the work is occurring, and that access will change day-to-day. The Contractor will help direct folks as needed for local access, however, there may be times where pedestrians/vehicles will need to go around the block to get in/out of E Wilson St from one side or the other. Sidewalk access on the north-side will be returned after working hours as much as possible, however, overnight closures are possible. Sidewalk on the south-side of the 100 Block of E Wilson St continues to be closed due to Findorff’s construction at 109 E Wilson St.
100 Block of E Wilson St Overview
View past project updates »Project Details
Project Information
Project Overview
The City is planning the reconstruction of E Wilson St from MLK Blvd to S Franklin St and E Doty St from MLK Blvd to King St in 2024. The project improvements include replacement of existing pavement and pavement base, curb and gutter, sanitary sewer main and laterals, storm sewer, and porting of the water main. Damaged sections of sidewalk will also be replaced or as needed to install sewer service laterals. In addition, a new cycle track will be installed along E Wilson St as part of this project.
Project Limits
E Wilson St – Martin Luther King Jr Blvd to S Franklin St
E Doty St - Martin Luther King Jr Blvd to King St
Project Schedule
Start of Construction – April 2024 (tentative)
End of Construction – October 2024 (tentative)
Business Resources
City's Road Reconstruction Business Guide
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
A public information meeting was held on Dec. 7, 2023. Thank you to all who attended. Materials presented at the meeting, along with a video recording of the meeting may be accessed under project updates.
City Process, Meetings
Common Council: 01/ 23/ 2024 (Tentative)
Board of Public Works: 01/ 10/ 2024
Mailings
Board of Public Works Public Hearing (July 10, 2024): Schedule of Assessments
Letter to property owners, Fact and Detail Sheet, Assessments (Dec. 26, 2023)
Common Council Public Hearing January 24, 2024: Public Hearing Notice, Assessments
Start of Construction Mailing: Fact and Details Sheet