New Sidewalk Installation -- 2022
August 26, 2022 Update
Construction is scheduled to start on Monday, September 12, 2022. Next week, City Engineering will be mailing a letter with information and details regarding the project to residents impacted by construction work.
If you have questions or concerns regarding this project, please contact the Project Manager, Fadi El Musa, at felmusagonzalez@cityofmadison.com
View past project updates »Project Details
Project Information
Project Overview
In 2022, the City of Madison is proposing the construction of new concrete sidewalk at different locations throughout the City to fill gaps and connect existing sections of sidewalk. In addition, intersection crossings will be evaluated and improved as needed.
View the City of Madison Sidewalk Data Map which shows current locations with existing sidewalks.
Project Limits
Locations with missing sections of sidewalk have been identified as follows:
- Busse St, east side of 3700 block
- Johns St, both sides of 3600 block and a small section fronting 3526 Johns St.
- Judd St., west side of 100 block
- Walter St., east side Johns to Sargent.
- Royster Ave., west side from Olbrich to Sargent.
Project Schedule
April 2022: advertised for bids.
June 2022: anticipated start of construction.
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
Eastmoreland Community Association Public Information Meeting Presentation
City Meetings, Process
Transportation Commission: Presented on 10/27/2021
Board of Public Works: 3/16/2022
Common Council: 3/29/2022
Mailing
Project & Public Hearing Notice: 3/4/2022
Start of Construction Notice: 8/30/2022