Park Street Joint Repair

Last Updated: 08/23/2019

Construction Update

Park St/Badger Rd Intersection: Contractor will be closing Northbound lanes of Park St in the Badger Rd intersection August 24 & 25. One lane will remain open Northbound Park St and Westbound Badger Rd. Eastbound Badger Rd will have only one turn lane to northbound Park St and one through lane. Southbound Park St will be unaffected.

Construction in this intersection will occur over four weekends.

Phase III (Badger Rd to RR) is currently under construction until October 15.

Two lanes of inbound traffic will be open for peak hour morning commute: 7 am – 9 am.

All other times, inbound Park St may be reduced to one lane only in the active construction zone.

Project Description

The project will consist of removing and replacing bad concrete joints with new concrete. The contractor will saw cut the concrete full depth, 2.5’ on each side of the bad joint, remove the asphalt and concrete and install new concrete. There will also be full concrete slab replacement as needed, spot curb and gutter repair and installation of new crosswalk and bus pads at the Beld Street intersection. In general, one northbound (NB) lane of South Park Street will be paved at a time to maintain as much traffic flow as possible. Parking may be removed and the east curb lane may be used as a travel lane during peak hours.

Project Limits

The project limits for the work are 2 separate section of concrete repairs on inbound lanes only. The south section is S. Park Street from W. Badger Rd. to the Railroad Crossing and the North section is S. Park St. from 100 feet south of W. Olin Ave to W. Washington Ave

Project Schedule

Tentative Start date is June 10th with completion date of the north section by August 10th and completion of the south section by October 15th.