Pleasant View Road

August 8, 2024 Update

Pleasant View Road from Timber Wolf Trail to USH 14 is complete.

The roadway design of Pleasant View Road from Mineral Point Road to Timber Wolf Trail is currently on hold at 60% design awaiting construction funding. Construction is not scheduled at this time. Once the project resumes design, an update will be provided here about the design and construction schedule.

View past project updates »

Project Details

  • Location

    • 3300 North Pleasant View Road
      Madison, WI 53593
  • Project Type

  • Status

    Completed
  • Estimated Schedule

  • Impact

    Major
  • Alder District

    District 9

Project Information

Project Overview

Pleasant View Road will be reconstructed from Mineral Point Road to US 14 as part of a joint project with the City of Middleton. The proposed project will include reconstruction of the existing roadway as an urban four-lane arterial with new pavement and gravel as well as the addition of curb and gutter, a raised median, new multi-use path/sidewalk in selected areas, storm sewer, sanitary sewer and water main. Other improvements include new retaining walls, street lighting, pavement marking, signing, and storm water detention ponds.

You can now view the Overall Project Exhibit. 

As a result of the October 13, 2021 Public Information Meeting for Swallowtail Pond, the southern path was revised.  The revised exhibit is found below.

Figure showing the proposed grading and normal water surface for Swallowtail Pond.  Graphic also shows the paths to be placed around the pond and its proximity to Pleasant View Road.
Swallowtail Pond Conceptual Layout

Project Limits

Phase 1 – Timber Wolf Trail to US Highway 14

Phase 2 – Mineral Point Road to Timber Wolf Trail

Project Schedule

Construction Phase 1: Fall 2022, spring/summer/fall 2023, spring/early summer 2024

Construction Phase 2: Earliest 2026 (No funding available at this time)

30% Design - Fall 2018

The 30% design for the project is complete. As part of the 30% design, roundabouts were selected by the City of Madison and Middleton at the Elderberry, Blackhawk, Greenway and Quarry intersections with Pleasant View Road. The Old Sauk Road and US 14 intersections with Mineral Point Road will remain signalized intersections. An exhibit showing the proposed street layout can be found here: Pleasant View Plans

60% Design - 2019

The 60% design for Phase 1 of the project is complete. The 60% design for Phase 2 is complete.

75% Design - 2020

The 75% design for Phase 1 of the project is complete. Phase 2 will remain at 60% design until funding becomes available.

90% Design - 2021

The 90% design for Phase 1 of the is complete.

Public Involvement 

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:

Public Information Meetings

WisDOT, City of Madison, City of Middleton, and the Contractor held a public information meeting from 5:30-7:30 p.m. on Wednesday, March 8, 2023 in the Middleton Public Library located at 7425 Hubbard Avenue, Middleton. The open house format meeting discussed the upcoming improvements, construction schedule, and expected street closures/detours in 2023.

View the March 8, 2023 Public Information Meeting Handout

Oct. 13, 2021 Public Information Meeting Recording

June 28, 2018 Public Information Meeting Handout
June 28, 2018 Public Information Meeting Exhibits
June 28, 2018 Public Information Meeting Roundabout Alternative Exhibit
June 28, 2018 Public Information Meeting Signal Alternative Exhibit

Public Informational Mailer

The project team mailed out a public postcard to inform property owners and residents along and near Pleasant View Road of the proposed roadway design Oct. 27, 2020.
Oct. 27 Proposed Roadway Design Postcard
Overall Project Exhibit

City Meetings, Process 

Transportation Commission: Project introduced Oct. 24, 2018
Transportation Commission: Project approved Nov. 28, 2018
Board of Public Works: Approved Dec, 12, 2018
Common Council: Approved Jan. 8, 2019
Board of Public Works Hearing to Approve Plans, Specifications and Assessments: Sept. 22, 2021
Common Council Public Hearing to Approve Plans, Specifications and Assessments: Oct. 5, 2021

Project Updates

August 8, 2024 Update

Pleasant View Road from Timber Wolf Trail to USH 14 is complete.

The roadway design of Pleasant View Road from Mineral Point Road to Timber Wolf Trail is currently on hold at 60% design awaiting construction funding. Construction is not scheduled at this time. Once the project resumes design, an update will be provided here about the design and construction schedule.

July 23, 2024 Update

Major construction operations are complete along Pleasant View Road.

Pleasant View Road is open between Old Sauk Road to US 14. There are no more planned full closures anticipated.

The contractor is completing final restoration throughout the project.

The City of Middleton's path over Pleasant View Road and connects to Pleasant View Road is open.

June 3, 2024 Update

Major construction operations along Pleasant View Road will be complete by the end of June 2024.

Pleasant View Road is open between Old Sauk Road to US 14. There are no more planned full closures anticipated.

Blackhawk Road (east and west of Pleasant View Road) is open. The contractor is working on the roundabout, single lane closures and restricted turning movements are ongoing to complete the work.

Greenway Boulevard at Pleasant View Road is open. The contractor is working on the roundabout, single lane closures and restricted turning movements are ongoing to complete the work.

The contractor is working on asphalt paving, pavement marking, and soil restoration, retaining walls, retaining wall fencing, and removal of temporary formwork from the new retaining walls between Blackhawk Road and the Quarry Road.

The City of Middleton's path that connects to Pleasant View Road is closed until the contractor completes the new path bridge over the street in the spring of 2024.

WisDOT is the project lead for construction. Please send us your comments and questions and we will work with the WisDOT construction inspector to provide answers. Jim Grender from CGC, Inc. has been hired by WisDOT as the construction engineer and his contact information shall you need it is 608-712-0533 or jgrender@cgcinc.net.

May 10, 2024 Update

Pleasant View Road is open between Old Sauk Road to US 14. There are no planned full closures scheduled at this time.

Beginning the week of May 13, the Pleasant View Road southbound traffic will switch to the newly constructed southbound lanes between Blackhawk Road and Quarry Road. Also the temporary signal at Blackhawk Road will be removed as the constructor continues to work on the roundabout. Turning movements will be restricted at the Blackhawk Road intersection for the roundabout construction.

Blackhawk Road (east and west of Pleasant View Road) is open. The contractor is working on the roundabout, single lane closures and restricted turning movements are anticipated to complete the work.

Greenway Boulevard at Pleasant View Road is open. The contractor is working on the roundabout, single lane closures and restricted turning movements are anticipated to complete the work.

The contractor is working on the street lighting installation, grading, concrete work, asphalt paving, pavement marking, temporary pavement marking removal, pedestrian bridge, retaining walls, retaining wall fencing, and removal of temporary formwork from the new retaining walls between Blackhawk Road and the Quarry Road.

The City of Middleton's path that connects to Pleasant View Road is closed until the contractor completes the new path bridge over the street in the spring of 2024.

WisDOT is the project lead for construction. Please send us your comments and questions and we will work with the WisDOT construction inspector to provide answers. Jim Grender from CGC, Inc. has been hired by WisDOT as the construction engineer and his contact information shall you need it is 608-712-0533 or jgrender@cgcinc.net.

April 25, 2024 Update

Pleasant View Road remains open between Greenway Boulevard and Quarry Road. Traffic is able to travel from Old Sauk Road to US 14. There are no planned full closures scheduled at this time.

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Timber Wolf Trail to Blackhawk Road.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Blackhawk Road to Greenway Boulevard.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Greenway Boulevard to Quarry Road, except during the closure noted above.

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Quarry Road to US 14.

Blackhawk Road (east and west of Pleasant View Road) is open for 2-way traffic. The contractor will finish the Pleasant View Road and Blackhawk Road intersection in the spring of 2024, single lane closures are anticipated to complete the work.

Greenway Boulevard at Pleasant View Road is open. The contractor will finish the Pleasant View Road and Greenway Boulevard intersection in the spring of 2024, single lane closures are anticipated to complete the work.

The contractor is working on the temporary asphalt removal, storm sewer, street lighting installation, grading, concrete work, pedestrian bridge, retaining walls, retaining wall fencing, and removal of temporary formwork from the new retaining walls along the west side of the street from Blackhawk Road to the Quarry Road.

The City of Middleton's path that connects to Pleasant View Road is closed until the contractor completes the new path bridge over the street in the spring of 2024.

WisDOT is the project lead for construction. Please send us your comments and questions and we will work with the WisDOT construction inspector to provide answers. Jim Grender from CGC, Inc. has been hired by WisDOT as the construction engineer and his contact information shall you need it is 608-712-0533 or jgrender@cgcinc.net.

April 24, 2024 Update

Pleasant View Road between Quarry Road and the Pleasant View Golf Course will be closed April 26, 2024 from 9am to 2pm for work on the new pedestrian bridge.

Pleasant View Road remains open between Greenway Boulevard and Quarry Road. Traffic is able to travel from Old Sauk Road to US 14, except during the closure noted above.

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Timber Wolf Trail to Blackhawk Road.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Blackhawk Road to Greenway Boulevard.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Greenway Boulevard to Quarry Road, except during the closure noted above.

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Quarry Road to US 14.

Blackhawk Road (east and west of Pleasant View Road) is open for 2-way traffic. The contractor will finish the Pleasant View Road and Blackhawk Road intersection in the spring of 2024, single lane closures are anticipated to complete the work.

Greenway Boulevard at Pleasant View Road is open. The contractor will finish the Pleasant View Road and Greenway Boulevard intersection in the spring of 2024, single lane closures are anticipated to complete the work.

The contractor is working on the temporary asphalt removal, storm sewer, street lighting installation, grading, concrete work, pedestrian bridge, retaining walls, retaining wall fencing, and removal of temporary formwork from the new retaining walls along the west side of the street from Blackhawk Road to the Quarry Road.

The City of Middleton's path that connects to Pleasant View Road is closed until the contractor completes the new path bridge over the street in the spring of 2024.

WisDOT is the project lead for construction. Please send us your comments and questions and we will work with the WisDOT construction inspector to provide answers. Jim Grender from CGC, Inc. has been hired by WisDOT as the construction engineer and his contact information shall you need it is 608-712-0533 or jgrender@cgcinc.net.

April 11, 2024 Update

Pleasant View Road remains open between Greenway Boulevard and Quarry Road. Traffic is able to travel from Old Sauk Road to US 14.

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Timber Wolf Trail to Blackhawk Road.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Blackhawk Road to Greenway Boulevard.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Greenway Boulevard to Quarry Road, except during the closure noted above.

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Quarry Road to US 14.

Blackhawk Road (east and west of Pleasant View Road) is open for 2-way traffic. The contractor will finish the Pleasant View Road and Blackhawk Road intersection in the spring of 2024, single lane closures are anticipated to complete the work.

Greenway Boulevard at Pleasant View Road is open. The contractor will finish the Pleasant View Road and Greenway Boulevard intersection in the spring of 2024, single lane closures are anticipated to complete the work.

The contractor is working on the temporary asphalt removal, storm sewer, street lighting installation, grading, concrete work, pedestrian bridge, retaining walls, retaining wall fencing, and removal of temporary formwork from the new retaining walls along the west side of the street from Blackhawk Road to the Quarry Road.

The City of Middleton's path that connects to Pleasant View Road is closed until the contractor completes the new path bridge over the street in the spring of 2024.

WisDOT is the project lead for construction. Please send us your comments and questions and we will work with the WisDOT construction inspector to provide answers. Jim Grender from CGC, Inc. has been hired by WisDOT as the construction engineer and his contact information shall you need it is 608-712-0533 or jgrender@cgcinc.net.

April 8, 2024 Update

Pleasant View Road between Quarry Road and the Pleasant View Golf Course will be closed April 10, 2024 from 9am to 2pm for concrete placement on the new pedestrian bridge. 

Pleasant View Road remains open between Greenway Boulevard and Quarry Road. Traffic is able to travel from Old Sauk Road to US 14, except during the closure noted above.

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Timber Wolf Trail to Blackhawk Road.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Blackhawk Road to Greenway Boulevard.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Greenway Boulevard to Quarry Road, except during the closure noted above.

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Quarry Road to US 14.

Blackhawk Road (east and west of Pleasant View Road) is open for 2-way traffic. The contractor will finish the Pleasant View Road and Blackhawk Road intersection in the spring of 2024, single lane closures are anticipated to complete the work.

Greenway Boulevard at Pleasant View Road is open. The contractor will finish the Pleasant View Road and Greenway Boulevard intersection in the spring of 2024, single lane closures are anticipated to complete the work.

The contractor is working on the temporary asphalt removal, storm sewer, street lighting installation, grading, concrete work, pedestrian bridge, and retaining walls along the west side of the street from Blackhawk Road to the Quarry Road.

The City of Middleton's path that connects to Pleasant View Road is closed until the contractor completes the new path bridge over the street in the spring of 2024.

WisDOT is the project lead for construction. Please send us your comments and questions and we will work with the WisDOT construction inspector to provide answers. Jim Grender from CGC, Inc. has been hired by WisDOT as the construction engineer and his contact information shall you need it is 608-712-0533 or jgrender@cgcinc.net

April 1, 2024 Update

Pleasant View Road construction has resumed.

Due to weather, Pleasant View Road didn't close on March 28, 2024 between Greenway Boulevard and Quarry Road for placement of concrete on the pedestrian bridge. The work will be rescheduled and another update will be posted to the website once a date is available.

Traffic patterns discussed below will be maintained for the weeks ahead. Any temporary closures of the street for the bridge construction will be posted to the website.

Pleasant View Road remains open between Greenway Boulevard and Quarry Road. Traffic is able to travel from Old Sauk Road to US 14.

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Timber Wolf Trail to Blackhawk Road.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Blackhawk Road to Greenway Boulevard.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Greenway Boulevard to Quarry Road.

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Quarry Road to US 14.

Blackhawk Road (east and west of Pleasant View Road) is open for 2-way traffic. The contractor will finish the Pleasant View Road and Blackhawk Road intersection in the spring of 2024.

Greenway Boulevard at Pleasant View Road is open. The contractor will finish the Pleasant View Road and Greenway Boulevard intersection in the spring of 2024.

The contractor is working on the temporary asphalt removal, storm sewer, street lighting installation, grading, concrete work, and retaining walls along the west side of the street from Blackhawk Road to the Quarry Road.

The City of Middleton's path that connects to Pleasant View Road is closed until the contractor completes the new path bridge over the street in the spring of 2024.

WisDOT is the project lead for construction. Please send us your comments and questions and we will work with the WisDOT construction inspector to provide answers. Jim Grender from CGC, Inc. has been hired by WisDOT as the construction engineer and his contact information shall you need it is 608-712-0533 or jgrender@cgcinc.net

March 25, 2024 Update

Concrete placement for the pedestrian bridge over the street for the future Middleton path connection will be on March 28, 2024. Pleasant View Road will be closed between 9 am and 2 pm for the pedestrian bridge work.

March 20, 2024 Update

Pleasant View Road construction has resumed. 

The contractor successfully completed placing the pedestrian bridge over street for the future Middleton path connection. The next step is to place the concrete deck on the bridge. The website will be updated once a date for the concrete placement is determined.

Traffic patterns discussed below will be maintained for the weeks ahead. Any temporary closures of the street for the bridge construction will be posted to the website.

Pleasant View Road remains open between Greenway Boulevard and Quarry Road. Traffic is able to travel from Old Sauk Road to US 14.

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Timber Wolf Trail to Blackhawk Road.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Blackhawk Road to Greenway Boulevard.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Greenway Boulevard to Quarry Road.

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Quarry Road to US 14.

All work on US 14 at Pleasant View Road is complete.

Blackhawk Road (east and west of Pleasant View Road) is open for 2-way traffic. The contractor will finish the Pleasant View Road and Blackhawk Road intersection in the spring of 2024.

Greenway Boulevard at Pleasant View Road is open. The contractor will finish the Pleasant View Road and Greenway Boulevard intersection in the spring of 2024.

The contractor is working on the temporary asphalt removal, storm sewer, street lighting installation, grading, concrete work, and retaining walls along the west side of the street from Blackhawk Road to the Quarry Road.

The City of Middleton's path that connects to Pleasant View Road is closed until the contractor completes the new path bridge over the street in the spring of 2024.

WisDOT is the project lead for construction. Please send us your comments and questions and we will work with the WisDOT construction inspector to provide answers. Jim Grender from CGC, Inc. has been hired by WisDOT as the construction engineer and his contact information shall you need it is 608-712-0533 or jgrender@cgcinc.net

March 14, 2024 Update

Pleasant View Road construction has resumed. The contractor will be closing down Pleasant View Rd between Quarry Rd and the Pleasant View Golf Course March 19 and March 21 from 9am to 2pm to place girders above the street for the future pedestrian bridge. 

Traffic patterns discussed below will be maintained for the weeks ahead except for the closure discussed above. 

Pleasant View Road remains open between Greenway Boulevard and Quarry Road. Traffic is able to travel from Old Sauk Road to US 14. 

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Timber Wolf Trail to Blackhawk Road. 

Traffic on Pleasant View Road is open on the east side 2-lane portion from Blackhawk Road to Greenway Boulevard.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Greenway Boulevard to Quarry Road. 

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Quarry Road to US 14.

All work on US 14 at Pleasant View Road is complete. 

Blackhawk Road (east and west of Pleasant View Road) is open for 2-way traffic. The contractor will finish the Pleasant View Road and Blackhawk Road intersection in the spring of 2024.

Greenway Boulevard at Pleasant View Road is open. The contractor will finish the Pleasant View Road and Greenway Boulevard intersection in the spring of 2024.

The contractor is working on the temporary asphalt removal, storm sewer, street lighting installation, grading, concrete work, and retaining walls along the west side of the street from Blackhawk Road to the Quarry Road. 

The City of Middleton's path that connects to Pleasant View Road is closed until the contractor completes the new path bridge over the street in the spring of 2024.

WisDOT is the project lead for construction. Please send us your comments and questions and we will work with the WisDOT construction inspector to provide answers. Jim Grender from CGC, Inc. has been hired by WisDOT as the construction engineer and his contact information shall you need it is 608-712-0533 or jgrender@cgcinc.net

March 7, 2024 Update

Pleasant View Road construction will resume March 11, 2024. Traffic patterns discussed below will be maintained for the weeks ahead. Upcoming traffic pattern changes will be posted here once they are available.

Pleasant View Road remains open between Greenway Boulevard and Quarry Road. Traffic is able to travel from Old Sauk Road to US 14. 

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Timber Wolf Trail to Blackhawk Road. 

Traffic on Pleasant View Road is open on the east side 2-lane portion from Blackhawk Road to Greenway Boulevard.

Traffic on Pleasant View Road is open on the east side 2-lane portion from Greenway Boulevard to Quarry Road. 

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Quarry Road to US 14.

All work on US 14 at Pleasant View Road is complete. 

Blackhawk Road (east and west of Pleasant View Road) is open for 2-way traffic. The contractor will finish the Pleasant View Road and Blackhawk Road intersection beginning in March 2024.

Greenway Boulevard at Pleasant View Road is open. The contractor will finish the Pleasant View Road and Greenway Boulevard intersection beginning in March 2024.

The contractor is working on the temporary asphalt removal, storm sewer, street lighting installation, grading, concrete work, and retaining walls along the west side of the street from Blackhawk Road to the Quarry Road. 

The City of Middleton's path that connects to Pleasant View Road is closed until the contractor completes the new path bridge over the street which is anticipated in spring of 2024. The bridge work will begin in March 2024.

WisDOT is the project lead for construction. Please send us your comments and questions and we will work with the WisDOT construction inspector to provide answers. Jim Grender from CGC, Inc. has been hired by WisDOT as the construction engineer and his contact information shall you need it is 608-712-0533 or jgrender@cgcinc.net

January 5, 2024 Update

Pleasant View Road will reopen between Greenway Boulevard and Quarry Road the afternoon of January 12. Traffic will be able to travel from Old Sauk Road to US 14. 

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Timber Wolf Trail to Blackhawk Road. 

Traffic on Pleasant View Road is open on the east side 2-lane portion from Blackhawk Road to Greenway Boulevard.

Traffic on Pleasant View Road will be open on the east side 2-lane portion from Greenway Boulevard to Quarry Road beginning January 12. 

Traffic on Pleasant View Road will be open on the 4-lane portion of the street from Quarry Road to US 14 beginning January 12.

All work on US 14 at Pleasant View Road is complete. 

Blackhawk Road (east and west of Pleasant View Road) is open for 2-way traffic. The contractor will finish the Pleasant View Road and Blackhawk Road intersection in the spring of 2024.

Greenway Boulevard at Pleasant View Road is open. The contractor will finish the Pleasant View Road and Greenway Boulevard intersection in the spring of 2024.

The contractor is working on the temporary asphalt removal, storm sewer, street lighting installation, grading, concrete work, and retaining walls along the west side of the street from Blackhawk Road to the Quarry Road. The work is anticipated to be complete by the spring of 2024.

The City of Middleton's path that connects to Pleasant View Road is closed until the contractor completes the new path bridge over the street which is anticipated in spring of 2024.

WisDOT is the project lead for construction. Please send us your comments and questions and we will work with the WisDOT construction inspector to provide answers. Jim Grender from CGC, Inc. has been hired by WisDOT as the construction engineer and his contact information shall you need it is 608-712-0533 or jgrender@cgcinc.net

November 9, 2023 Update

Pleasant View Road remains closed between Greenway Boulevard and Quarry Road until late-December. Access will be maintained to the Pleasant View Road Golf Course via Pleasant View Road traveling from the south. A detour is posted utilizing USH 14, Beltline and Old Sauk Road. 2-way traffic access on Pleasant View Road will be maintained between Old Sauk Road and Greenway Boulevard for local traffic and residents.

The Timber Wolf Lane entrance at Pleasant View Road is open. 

Traffic on Pleasant View Road is open on the 4-lane portion of the street from Timber Wolf Trail to Blackhawk Road. Traffic is on the east side 2-lane portion from Blackhawk Road to the Golf Course. This traffic pattern will remain in place until late-late December 2024.

Blackhawk Road (east and west of Pleasant View Road) is open for 2-way traffic. The contractor will finish the Pleasant View Road and Blackhawk Road intersection in the spring of 2024.

Greenway Boulevard at Pleasant View Road is open. The contractor will finish the Pleasant View Road and Greenway Boulevard intersection in the spring of 2024.

The contractor is working on the temporary asphalt removal, storm sewer, street lighting installation, grading, concrete work, and retaining walls along the west side of the street from Blackhawk Road to the Quarry Road. The work is anticipated to be complete by the spring of 2024.

The City of Middleton's path that connects to Pleasant View Road is closed until the contractor completes the new path bridge over the street which is anticipated in spring of 2024.

The Pleasant View Road and Quarry Road intersection is finishing up with asphalt placement, pavement marking, and permanent signing. The work is anticipated to be complete by the end of November.

Pleasant View Road is open at Quarry Road from US 14.

The work at the US 14 and Pleasant View Road intersection will finish up with Traffic Signal modifications, concrete work, pavement marking, permanent signing, restoration (topsoil & seed), and railroad work. The work is anticipated to be complete by the end of December.

Sanitary sewer and water main work throughout the project are complete.

Rock blasting is complete north of the golf course entrance.

Swallowtail pond earthwork is complete. 

Madison Gas & Electric continues to perform gas main work between Blackhawk Road and Quarry Road through December.

WisDOT is the project lead for construction. Please send us your comments and questions and we will work with the WisDOT construction inspector to provide answers. Jim Grender from CGC, Inc. has been hired by WisDOT as the construction engineer and his contact information shall you need it is 608-712-0533 or jgrender@cgcinc.net

Was this page helpful to you?