October 3, 2024 Update

Quarter 4 Update
The pole mount portion of this project (42.66 kW) will be complete in Oct/Nov. 2024.  The roof top portion of the project has been delayed until quarter 3 and quarter 4 of 2025.

View past project updates »

Project Details

  • Location

    • 809 S. Thompson Dr.
      Madison, WI 53716
  • Project Type

  • Status

    Construction
  • Estimated Schedule

  • Alder District

    District 3

Project Information

Project Overview

Installation of a roughly 100 kW solar photovoltaic system at the Madison Police Department East District Station. The system will be a combination of roof mounted and ground mounted modules and will produce an estimated 131,000 kWh per year. When combined with the building’s existing ground mounted system, 85% of the building’s electricity usage will be generated by the solar arrays. The array will be installed by the Engineering Division’s GreenPower program where trainees with little to no electrical skills are provide on-the-job training through solar installations on City buildings.

Project Schedule

City User Agency: Madison Police Dept.

Planning and Design: Jan – June 2022

Site work for ground mounted modules in early 2022

Construction Start Date: December 2023
Expected Completion Date: Quarter 4 2025

Project Updates

October 3, 2024 Update

Quarter 4 Update
The pole mount portion of this project (42.66 kW) will be complete in Oct/Nov. 2024.  The roof top portion of the project has been delayed until quarter 3 and quarter 4 of 2025.

January 4, 2024 Update

The project status has moved into Construction with expected completion by June 2024.