Walter Street Restrooms @ Olbrich Park
Project Details
Project Information
Follow the progress on our FLICKR page!
UPDATE: April 29, 2019
Added: Follow the progress on our FLICKR page!
New Restrooms/Shelter
Replacing the restroom building at Olbrich Park (Walter Street location).
City User Agency: Parks Division
Design and Planning: Fall 2017
1st Advertisement of Bid: June 25, 2018 Documents available on Bid Express.
Bid Due: Thursday, July , 2018 at 2:00 pm
Construction Start: Oct. 1, 2018
Expected Completion: May 31, 2019
Construction Pre-Bid Meeting: July 10, 2018 2:00 pm at the site, 502 Walter St., Madison, WI
SBE Pre-Bid Meeting: July 27, 2018 1:00 pm at 1600 Emil St., Madison, WI
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
New Restroom/Shelter Rendering
(subject to change during the next phase of the design process)