Warner Beach Park Shelter
Last Updated: 01/19/2021
Updated: Oct. 06, 2020
Warner Beach Park Shelter in the NEWS:
Oct. 06, 2020: City of Madison News Updates
Construction Underway on New Warner Park Beach Shelter
Follow the Progress on our FLICKR page!
Visit the project site virtually on EarthCam®!
Sept. 30, 2020: Construction on the Warner Beach Park Shelter officially started onsite the day after Labor Day, Sept. 8th. Asbestos abatement and demo was completed on the existing shelter to make way for the staking and excavation for the new shelter. As of this week, footings have been poured and forms are being set for the foundation walls. Follow our Flickr and EarthCam links to watch this building site take shape!
New Restrooms/Shelter
City Engineering will be replacing the existing beach house with a new park shelter and restrooms at Warner Beach. The building will also include a pump room as part of the Clean Beach system announced in August 2019, a joint project between the City of Madison and Dane County. Warner Beach Park Shelter will be the fifth prototype park shelter and restrooms. Previous prototype shelters are located at Lake Edge Park; Esther Beach; Penn Park and Walter Street at Olbrich Park.
For more information on the Public Information meeting on this project, please visit Warner Park - Beach Shelter Replacement.
City User Agency: Parks Division
Design and Planning: December - April 2020
Pre-Bid Building/Site Tour: Wednesday, June 24, 2020 @ 10:00 am at the project site, 1101 Woodward Dr.
Bid Due Date: July 09, 2020
Construction Start date: Sept. 8, 2020
Expected Completion date: April 30, 2021
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
Restroom/Shelter Rendering Updated March 11, 2020:
(subject to change during the next phase of the design process)
Warner Beach Park Shelter in the NEWS:
Oct. 06, 2020: City of Madison News Updates
Construction Underway on New Warner Park Beach Shelter
Project History:
Awarding Public Works Contract No. 8850, Warner Beach Park Shelter
July 9, 2019 Public Meeting